Three-room apartment renovation on Pokrovska

Three-room apartment on Pokrovska

A three-room apartment on Pokrovska Street in Kyiv. Work ran from January 2018 to November 2019: demolition of partitions, closing up and cutting new openings, complete replacement of the wiring and plumbing, plastering and skim-coating, fitting out the bathrooms with underfloor heating, finish work and furniture installation. The layout was partly reworked — the kitchen was merged with the living room, and several rooms received built-in wardrobes and decorative drywall niches.

Turnkey apartment renovation in Kyiv
Start
January 2018
Completed
November 2019
Photo record
22 months
Stages
7
Photos
105

Client

Name withheldKyiv
Project address
••••••••• St, ••
Type
Apartment
Rooms
9
Duration
22 months
Stages
7
Photo report
105

The client's name, photo and exact address are withheld. In their own account they see all of it.

Responsible for the project

Viacheslav MelnykViacheslav MelnykFounder of Archideal · general contractor

Runs the project himself: signs off stages, signs the certificates, answers the phone.

+380 67 679 59 79
Stages
7
Photos
105
Approvals
19

Stage schedule

7 stages · 105 photos

January 2018 — November 2019

Demolition
Utilities and services
First fix
Plastering
Finishing
Furniture and fittings
Completed

The bars are built from the dates the photographs were taken, not drawn by hand — which is why stages overlap. On a real site something is always being finished while the next trade has already started.

Estimate

In a working account this shows amounts per stage, payments made and the balance. In the demo they are hidden.

Demolition
CompletedAmount
4 ******₴amount hidden
Utilities and services
CompletedAmount
9 ******₴amount hidden
First fix
CompletedAmount
4 ******₴amount hidden
Plastering
CompletedAmount
3 ******₴amount hidden
Finishing
CompletedAmount
6 ******₴amount hidden
Furniture and fittings
CompletedAmount
9 ******₴amount hidden
Completed
CompletedAmount
3 ******₴amount hidden
Total2 *******₴amount hidden

The amounts are hidden because this is someone else's project. You will see your own in your estimate, not on a website.

Approvals

Every decision that affects the money or the look is logged as its own item. Until the client marks it approved, work on that item does not start.

17 approved · 2 returned

ItemApproved byDateStatus
Electrical layout and outletsUtilities and servicesEngineerJanuary 24, 2018Approved
Water and drainage pointsUtilities and servicesEngineerFebruary 12, 2018Approved
Plaster typePlasteringEngineerMarch 17, 2018Approved
Reveals and external cornersPlasteringDesignerMarch 17, 2018Returned for revision
Reveals and external cornersPlastering · after revisionDesignerMarch 23, 2018Approved
Partition build-upFirst fixClientMarch 26, 2018Approved
Floor and ceiling levelsFirst fixClientMarch 30, 2018Approved
Heating layoutUtilities and servicesDesignerApril 22, 2018Approved
Demolition plan and setting outDemolitionDesignerMay 15, 2018Returned for revision
Survey and floor planDemolitionClientMay 15, 2018Approved
Demolition plan and setting outDemolition · after revisionDesignerMay 21, 2018Approved
Tile layoutFinishingClientApril 15, 2019Approved
Wall colourFinishingEngineerApril 15, 2019Approved
Floor finishFinishingEngineerApril 15, 2019Approved
Doors and hardwareFinishingEngineerApril 15, 2019Approved
Sanitaryware modelsFurniture and fittingsClientMay 13, 2019Approved
Handover checklistCompletedClientMay 15, 2019Approved
Kitchen drawingsFurniture and fittingsDesignerJune 9, 2019Approved
Light fittingsFurniture and fittingsClientJuly 13, 2019Approved

The approvals shown here are an example of how the mechanism works: the photographs do not record what was actually signed off on this project. Your account will carry your own history.

On site

  • Site managerdaily supervision and photo reports
  • Project managerestimate, schedule, contact with the client
  • Engineerdrawings and details

Rooms

How many frames each part of the project accounts for.

  • bedroom33
  • bathroom17
  • living room13
  • room7
  • kitchen5
  • hallway3
  • balcony3
  • corridor2
  • child's room2

Site log

Every day the site was photographed. The dates are real — read from the files, not typed in.

13 days photographed

  1. Furniture and fittingsNovember 26, 201921 photos

    Kitchen-living room with a marble splashback and pendants over the island · White cabinetry with patina, integrated appliances and a stone worktop

  2. Furniture and fittingsMay 8, 20193 photos

    Completed bedroom with curtains, coving and a dark floor · Light-filled bedroom with a wrought-iron chandelier and classic furniture

  3. Furniture and fittingsApril 19, 20192 photos

    Bedroom in beige tones with classic case goods · Patterned wallpaper behind the headboard, the other walls painted

  4. FinishingApril 15, 201910 photos

    Double socket in a wood-effect frame on vinyl wallpaper · Four-module bank with power, TV and internet sockets

  5. Utilities and servicesAugust 6, 20182 photos

    Bathroom with tiling laid and pipework brought out · Built-in niche within the tiling, front view

  6. Utilities and servicesJuly 30, 20181 photo

    Bathroom ceiling marked out for installation

  7. First fixJuly 11, 20181 photo

    Toilet installed, with pipework and wiring in the bathroom

  8. Utilities and servicesJune 25, 20181 photo

    Electrics and plumbing run together in the bathroom wall

  9. Utilities and servicesJune 5, 20184 photos

    Cable runs across the ceiling of a room · Ceiling with wiring and an opening for the chandelier

  10. DemolitionMay 15, 201817 photos

    An opening bricked up and ceiling chases with cable run through them · Bathroom with water supply and drainage rough-in complete

  11. Utilities and servicesApril 30, 20182 photos

    Metal framing in the living room, partly clad in moisture-resistant drywall · Electrical and service runs across the bathroom ceiling

  12. Utilities and servicesApril 23, 20182 photos

    Cable runs beneath the ceiling approaching the distribution points · Chases with cable, back boxes and junction boxes on the wall

  13. Utilities and servicesJanuary 18, 201812 photos

    Electrical cable laid in a chase cut into the wall · Bedroom with wiring pulled, viewed from the doorway

Documents

The contract, the estimate and the certificates live in the account, not in somebody's messenger.

  • Contract and annexesHidden
  • EstimateHidden
  • Certificates of completionHidden
  • Material specificationsHidden
  • As-built documentationHidden

Work in progress

Each stage is dates and frames from the site. These were shot for the job, not for a website, which is why some of them look exactly like a building site looks.

01

Demolition

May 20181 photo

Work completed

An opening bricked up and ceiling chases with cable run through them

May 15, 2018

02

Utilities and services

January 2018 — August 201830 photos

Work completed

Electrical cable laid in a chase cut into the wall

January 18, 2018

Bedroom with wiring pulled, viewed from the doorway

room · January 18, 2018

Cable runs beneath the ceiling approaching the distribution points

April 23, 2018

Chases with cable, back boxes and junction boxes on the wall

April 23, 2018

Metal framing in the living room, partly clad in moisture-resistant drywall

living room · April 30, 2018

Electrical and service runs across the bathroom ceiling

bathroom · April 30, 2018

Bathroom with water supply and drainage rough-in complete

bathroom · May 15, 2018

Ceiling with wiring run and an outlet point brought out

May 15, 2018

Junction boxes being fixed in place during the electrical rough-in

room · May 15, 2018

Hallway with open chases and a new drywall partition

hallway · May 15, 2018

Wiring run through the floor with the screed opened up

May 15, 2018

Wiring installed in the brick wall of the bathroom

bathroom · May 15, 2018

Cable runs and switch points set out in the kitchen-living room

May 15, 2018

Drywall boxing for services in the bedroom

bedroom · May 15, 2018

Hallway with wiring and socket positions marked out

corridor · May 15, 2018

Bathroom marked out before the services are run

bathroom · May 15, 2018

New opening cut through the brick wall and a bank of four back boxes

hallway · May 15, 2018

Drywall partition with the electrical layout marked out

May 15, 2018

Wiring in the wall before finishing work begins

room · May 15, 2018

Cable runs across the ceiling of a room

room · June 5, 2018

Ceiling with wiring and an opening for the chandelier

June 5, 2018

Wiring and a ventilation duct in the ceiling

June 5, 2018

Electrics and plumbing run together in the bathroom wall

June 25, 2018

Bathroom ceiling marked out for installation

bathroom · July 30, 2018

Bathroom with tiling laid and pipework brought out

bathroom · August 6, 2018

Built-in niche within the tiling, front view

bathroom · August 6, 2018

Taps and water outlets being fitted in the wall

Living room with wiring pulled, before finishing

living room

Underfloor heating mat laid out on the bathroom's concrete base

bathroom

Wiring and pipework brought together in one wall

03

First fix

January 2018 — July 201810 photos

Work completed

Walls after skim-coating, ready for painting

room · January 18, 2018

Bedroom with levelled walls, a PVC window and a radiator

bedroom · January 18, 2018

Empty room with a window, viewed from the doorway

January 18, 2018

Balcony with plastered walls and a floor screed

balcony · January 18, 2018

Wall fully clad in moisture-resistant drywall over the framing

May 15, 2018

Drywall joints filled and corners reinforced

May 15, 2018

Bedroom with a window and rough wiring brought out

bedroom · May 15, 2018

Toilet installed, with pipework and wiring in the bathroom

bathroom · July 11, 2018

Room with a window, prepared for finishing work

room

Rolls of WDS insulation with markings

04

Plastering

January 2018 — June 20188 photos

Work completed

Living room with plastered walls, a radiator and fresh screed

living room · January 18, 2018

Plastered walls and an unfinished opening with exposed brickwork

living room · January 18, 2018

Bedroom with a balcony door unit, radiator and electrical outlets

bedroom · January 18, 2018

Walls ready for painting and a PVC unit with balcony access

bedroom · January 18, 2018

Room at the plastering stage, viewed from the doorway

room · January 18, 2018

Balcony with cement plaster and plastered reveals

balcony · January 18, 2018

Plastered walls and ceiling, with a pier and lintel

June 5, 2018

Hallway with plastered walls, looking ahead

corridor

05

Finishing

April 20197 photos

Work completed

Double socket in a wood-effect frame on vinyl wallpaper

April 15, 2019

Four-module bank with power, TV and internet sockets

April 15, 2019

Entrance hall with white doors, cornice and tiling in the entry zone

hallway · April 15, 2019

Outdoor AC unit on brackets, seen through the balcony glazing

balcony

Part of the bathroom walls clad in large-format tile, heating mat on the floor

bathroom

Bathroom ceiling marked out for downlights

bathroom

Marble-effect porcelain on the walls, lower section still open

bathroom

06

Furniture and fittings

April 2019 — November 201913 photos

Work completed

Kitchen-living room with white cabinetry, an island and dark parquet

kitchen · April 15, 2019

Bedroom with dark parquet, a chandelier and furniture delivered

bedroom · April 15, 2019

Room with white furniture, recessed shelving and parquet

child's room · April 15, 2019

Bedroom with dark laminate and built-in drywall shelves

bedroom · April 15, 2019

Bedroom in beige tones with classic case goods

bedroom · April 19, 2019

Patterned wallpaper behind the headboard, the other walls painted

bedroom · April 19, 2019

Completed bedroom with curtains, coving and a dark floor

bedroom · May 8, 2019

Light-filled bedroom with a wrought-iron chandelier and classic furniture

bedroom · May 8, 2019

Room at move-in stage: furniture in place, boxes not yet unpacked

bedroom · May 8, 2019

Kitchen-living room with a marble splashback and pendants over the island

kitchen · November 26, 2019

White cabinetry with patina, integrated appliances and a stone worktop

kitchen · November 26, 2019

Full-wall built-in wardrobe with panelled fronts

bedroom

Kitchen-living room and hallway: parquet, tile at the entry, dark doors

kitchen

07

Completed

April 2019 — November 201936 photos

Completed and handed over — Final photographs, after cleaning and handover.

Bathroom with a built-in tub, twin basins and a towel radiator

bathroom · April 15, 2019

Living room with a seating area, downlights and an air conditioner

living room · April 15, 2019

Living room combined with the kitchen area and a breakfast bar

living room · April 15, 2019

Shower with a floor drain and glass door, black marble-effect floor

bathroom · November 26, 2019

Shower area with a recessed shelf and rain shower head

bathroom · November 26, 2019

Living room TV area with a white console and ceiling cornice

living room · November 26, 2019

Dining area by the bay glazing with a glass table

living room · November 26, 2019

Dining set under a chandelier with fabric shades

living room · November 26, 2019

Stretch ceiling with downlights above a round dining table

living room · November 26, 2019

Built-in tall unit with mirrored panels in the bathroom

bathroom · November 26, 2019

Corner of the bathroom with a tall storage unit and a framed mirror

bathroom · November 26, 2019

Bedroom with an upholstered headboard, wall-mounted TV and a floor-to-ceiling window

bedroom · November 26, 2019

Bedroom in a classic style with fine-patterned wallpaper

bedroom · November 26, 2019

Built-in wardrobe, panelled doors and moulded cornice in the bedroom

bedroom · November 26, 2019

Full-wall wardrobe with drawers and geometric wallpaper

bedroom · November 26, 2019

Workspace by the window and built-in decorative niches

bedroom · November 26, 2019

Full-wall bay window with sheers and drapes

bedroom · November 26, 2019

Fine-striped wallpaper and white case goods with a desk

bedroom · November 26, 2019

Full-wall built-in wardrobe in the child's bedroom

bedroom · November 26, 2019

Sliding wardrobe, interior door with architrave and ceiling cornice

bedroom · November 26, 2019

Corner of the bedroom with a display cabinet and latticework panels

bedroom · November 26, 2019

View from the hallway into the kitchen-living room and the tiled entry

kitchen · November 26, 2019

Three decorative drywall niches and a desk by the window

bedroom

Bedroom with a floor-to-ceiling window and a windowsill worktop

bedroom

Display cabinet and white MDF shelving unit in the corner of the bedroom

bedroom

Radiator under the window, ceiling cornice and wall shelves

bedroom

Studio with a living-dining area and a built-in kitchen with lighting

living room

Display cabinet with lattice fronts and a desk by the window

bedroom

Child's room with a bed, desk and wall shelves

child's room

Workspace by the floor-to-ceiling window and a niche with shelves

bedroom

Full-height built-in wardrobe with a moulded cornice

bedroom

Square drywall niches in a wall with light wallpaper

bedroom

White bedroom with parquet and a wardrobe with panelled fronts

bedroom

Living-dining room with a multi-level ceiling and pendants over the table

living room

Studio with a kitchen, dining area and under-cabinet task lighting

living room

Before-and-after collage: rough plaster and the finished bedroom interior

bedroom

Want the same account for your project?

We open the account on day one: the client sees stages, dates and photographs without waiting for a call from the site manager.

  • Access from the first day of work
  • Photo reports from site, not «all good»
  • Estimate, payments and balance in one place
+380 67 679 59 79

For example, +38 067 123 45 67

By sending this request you agree to our privacy policy.

Get a cost estimate