Commercial space renovation on Hoholivska

Commercial space on Hoholivska

A space on Hoholivska Street in Kyiv: a full-scale renovation from demolition to handover, carried out between February 2016 and December 2017. The basement floor and walls were stripped out, a trench was dug for utilities, pipes were replaced, and new plumbing, ventilation and electrics were installed. The finishing stage included plasterboard and suspended ceilings with downlights, painted walls, large-format porcelain stoneware on floors and stairs, and a tiled bathroom with fixtures; some rooms received polished concrete floors and a panoramic window.

Commercial fit-out in Kyiv
Start
February 2016
Completed
December 2017
Photo record
22 months
Stages
5
Photos
26

Client

Name withheldKyiv
Project address
••••••••• St, ••
Type
Commercial
Rooms
6
Duration
22 months
Stages
5
Photo report
26
Documents
2

The client's name, photo and exact address are withheld. In their own account they see all of it.

Responsible for the project

Viacheslav MelnykViacheslav MelnykFounder of Archideal · general contractor

Runs the project himself: signs off stages, signs the certificates, answers the phone.

+380 67 679 59 79
Stages
5
Photos
26
Approvals
13
Documents
2

Stage schedule

5 stages · 26 photos

February 2016 — December 2017

Demolition
Utilities and services
First fix
Finishing
Completed

The bars are built from the dates the photographs were taken, not drawn by hand — which is why stages overlap. On a real site something is always being finished while the next trade has already started.

Estimate

In a working account this shows amounts per stage, payments made and the balance. In the demo they are hidden.

Demolition
CompletedAmount
4 ******₴amount hidden
Utilities and services
CompletedAmount
9 ******₴amount hidden
First fix
CompletedAmount
4 ******₴amount hidden
Finishing
CompletedAmount
6 ******₴amount hidden
Completed
CompletedAmount
3 ******₴amount hidden
Total7 *******₴amount hidden

The amounts are hidden because this is someone else's project. You will see your own in your estimate, not on a website.

Approvals

Every decision that affects the money or the look is logged as its own item. Until the client marks it approved, work on that item does not start.

12 approved · 1 returned

ItemApproved byDateStatus
Survey and floor planDemolitionEngineerFebruary 3, 2016Returned for revision
Partition build-upFirst fixDesignerFebruary 3, 2016Approved
Floor and ceiling levelsFirst fixClientFebruary 3, 2016Approved
Survey and floor planDemolition · after revisionEngineerFebruary 9, 2016Approved
Demolition plan and setting outDemolitionClientFebruary 15, 2016Approved
Water and drainage pointsUtilities and servicesDesignerMarch 17, 2016Approved
Electrical layout and outletsUtilities and servicesClientMarch 22, 2016Approved
Heating layoutUtilities and servicesClientMarch 28, 2016Approved
Tile layoutFinishingDesignerAugust 17, 2016Approved
Wall colourFinishingClientAugust 17, 2016Approved
Floor finishFinishingDesignerAugust 17, 2016Approved
Doors and hardwareFinishingClientAugust 17, 2016Approved
Handover checklistCompletedDesignerDecember 1, 2016Approved

The approvals shown here are an example of how the mechanism works: the photographs do not record what was actually signed off on this project. Your account will carry your own history.

On site

  • Site managerdaily supervision and photo reports
  • Project managerestimate, schedule, contact with the client
  • Engineerdrawings and details

Rooms

How many frames each part of the project accounts for.

  • living room7
  • bathroom6
  • outdoors1
  • grounds1
  • corridor1
  • hallway1

Site log

Every day the site was photographed. The dates are real — read from the files, not typed in.

7 days photographed

  1. CompletedDecember 28, 20171 photo

    Bright room with red shelving units and wide window sills

  2. CompletedNovember 21, 20172 photos

    Finished salon reception area with a wooden reception desk · Lounge area with a polished concrete floor and a panoramic window

  3. Utilities and servicesAugust 17, 20169 photos

    Corridor with cable trunking installed and black doors fitted · Combined bathroom after tiling and installation of the fixtures

  4. Utilities and servicesApril 27, 20162 photos

    Installing the ventilation duct under the bathroom ceiling · Service floor with ceiling utilities and electrical wiring

  5. DemolitionMarch 17, 20163 photos

    The basement after the floor and wall structures were removed · Trench in the yard for laying the new utility lines

  6. Utilities and servicesMarch 3, 20161 photo

    Bathroom with utility connections and wiring brought out

  7. DemolitionFebruary 3, 20164 photos

    Facade of the residential building marked up for demolition before work began · Pipe routing marked out on the floor of the future bathroom

Documents

The contract, the estimate and the certificates live in the account, not in somebody's messenger. This project's archive holds 2 scanned documents — the documents themselves are closed in the demo.

  • Contract and annexesHidden
  • EstimateHidden
  • Certificates of completionHidden
  • Material specificationsHidden
  • As-built documentationHidden

Work in progress

Each stage is dates and frames from the site. These were shot for the job, not for a website, which is why some of them look exactly like a building site looks.

01

Demolition

February 2016 — March 20163 photos

Work completed

Facade of the residential building marked up for demolition before work began

outdoors · February 3, 2016

The basement after the floor and wall structures were removed

March 17, 2016

Trench in the yard for laying the new utility lines

grounds · March 17, 2016

02

Utilities and services

February 2016 — August 20167 photos

Work completed

Pipe routing marked out on the floor of the future bathroom

bathroom · February 3, 2016

Water supply pipes run beneath the bathroom ceiling

bathroom · February 3, 2016

Bathroom with utility connections and wiring brought out

bathroom · March 3, 2016

Brick wall with openings prepared for pipework

bathroom · March 17, 2016

Installing the ventilation duct under the bathroom ceiling

bathroom · April 27, 2016

Service floor with ceiling utilities and electrical wiring

April 27, 2016

Corridor with cable trunking installed and black doors fitted

corridor · August 17, 2016

03

First fix

February 20161 photo

Work completed

Office space after demolition, with a window and temporary lighting

February 3, 2016

04

Finishing

August 201610 photos

Work completed

Combined bathroom after tiling and installation of the fixtures

bathroom · August 17, 2016

Room with a suspended ceiling, downlights and uPVC windows

August 17, 2016

Multi-level plasterboard ceiling and porcelain stoneware in the large room

living room · August 17, 2016

Painted walls, porcelain stoneware with skirting and the distribution board installed

living room · August 17, 2016

Finishing wraps up: cleaning equipment and a section of electrics still exposed

living room · August 17, 2016

Commercial space with two shopfront windows and glass doors

August 17, 2016

Interfloor staircase with treads and risers clad in porcelain stoneware

hallway · August 17, 2016

Hall with three windows, sills and glossy porcelain stoneware

Empty room with a niche and a boxed-in duct after final finishing

Finished ceiling with cove lighting, window reveals and dark entrance doors

living room

05

Completed

August 2016 — December 20175 photos

Completed and handed over — Final photographs, after cleaning and handover.

Completed space with marble-effect porcelain stoneware and beige accents

living room · August 17, 2016

Finished salon reception area with a wooden reception desk

November 21, 2017

Lounge area with a polished concrete floor and a panoramic window

living room · November 21, 2017

Bright room with red shelving units and wide window sills

living room · December 28, 2017

Small room after renovation with neat reveals and window sills

Want the same account for your project?

We open the account on day one: the client sees stages, dates and photographs without waiting for a call from the site manager.

  • Access from the first day of work
  • Photo reports from site, not «all good»
  • Estimate, payments and balance in one place
+380 67 679 59 79

For example, +38 067 123 45 67

By sending this request you agree to our privacy policy.

Get a cost estimate