Three-room apartment renovation in Pozniaky

Three-room apartment in Pozniaky

A three-bedroom apartment in the Poznyaky district of Kyiv: a full renovation from demolition through to furnishing, carried out from January 2020 to February 2021. The layout was reworked with widened door openings and new brick partitions, the wiring and plumbing were fully replaced, and the job included plasterboard ceilings, stretch ceilings, decorative plaster finishes, marble-effect porcelain tile in the bathrooms and built-in furniture in every room. At the end, the heating system was checked with an infrared thermometer — radiator and floor temperature readings were recorded.

Turnkey apartment renovation in Kyiv
Start
January 2020
Completed
February 2021
Photo record
13 months
Stages
8
Photos
187

Client

Name withheldKyiv, Pozniaky
Project address
••••••••• St, ••
Type
Apartment
Rooms
11
Duration
13 months
Stages
8
Photo report
187
Documents
31

The client's name, photo and exact address are withheld. In their own account they see all of it.

Responsible for the project

Viacheslav MelnykViacheslav MelnykFounder of Archideal · general contractor

Runs the project himself: signs off stages, signs the certificates, answers the phone.

+380 67 679 59 79
Stages
8
Photos
187
Approvals
19
Documents
31

Stage schedule

8 stages · 187 photos

January 2020 — February 2021

Demolition
Utilities and services
First fix
Floor screed
Plastering
Finishing
Furniture and fittings
Completed

The bars are built from the dates the photographs were taken, not drawn by hand — which is why stages overlap. On a real site something is always being finished while the next trade has already started.

Estimate

In a working account this shows amounts per stage, payments made and the balance. In the demo they are hidden.

Demolition
CompletedAmount
4 ******₴amount hidden
Utilities and services
CompletedAmount
9 ******₴amount hidden
First fix
CompletedAmount
4 ******₴amount hidden
Floor screed
CompletedAmount
4 ******₴amount hidden
Plastering
CompletedAmount
3 ******₴amount hidden
Finishing
CompletedAmount
6 ******₴amount hidden
Furniture and fittings
CompletedAmount
9 ******₴amount hidden
Completed
CompletedAmount
3 ******₴amount hidden
Total2 *******₴amount hidden

The amounts are hidden because this is someone else's project. You will see your own in your estimate, not on a website.

Approvals

Every decision that affects the money or the look is logged as its own item. Until the client marks it approved, work on that item does not start.

17 approved · 2 returned

ItemApproved byDateStatus
Reveals and external cornersPlasteringEngineerFebruary 17, 2020Approved
Plaster typePlasteringDesignerMarch 5, 2020Approved
Wall colourFinishingClientMarch 19, 2020Approved
Partition build-upFirst fixEngineerMarch 27, 2020Approved
Demolition plan and setting outDemolitionDesignerMay 4, 2020Approved
Survey and floor planDemolitionDesignerMay 19, 2020Returned for revision
Survey and floor planDemolition · after revisionDesignerMay 25, 2020Approved
Doors and hardwareFinishingEngineerJune 25, 2020Approved
Heating layoutUtilities and servicesClientJuly 4, 2020Returned for revision
Tile layoutFinishingDesignerJuly 4, 2020Approved
Floor and ceiling levelsFirst fixClientJuly 5, 2020Approved
Water and drainage pointsUtilities and servicesEngineerJuly 7, 2020Approved
Heating layoutUtilities and services · after revisionClientJuly 10, 2020Approved
Floor finishFinishingEngineerJuly 22, 2020Approved
Handover checklistCompletedEngineerJuly 25, 2020Approved
Electrical layout and outletsUtilities and servicesDesignerAugust 1, 2020Approved
Kitchen drawingsFurniture and fittingsDesignerJanuary 1, 2021Approved
Light fittingsFurniture and fittingsDesignerJanuary 16, 2021Approved
Sanitaryware modelsFurniture and fittingsEngineerJanuary 26, 2021Approved

The approvals shown here are an example of how the mechanism works: the photographs do not record what was actually signed off on this project. Your account will carry your own history.

On site

  • Site managerdaily supervision and photo reports
  • Project managerestimate, schedule, contact with the client
  • Engineerdrawings and details

Rooms

How many frames each part of the project accounts for.

  • bathroom34
  • hallway25
  • living room22
  • bedroom20
  • corridor14
  • child's room12
  • kitchen11
  • room10
  • balcony2
  • living-bedroom1
  • study1

Site log

Every day the site was photographed. The dates are real — read from the files, not typed in.

32 days photographed

  1. Furniture and fittingsFebruary 25, 202122 photos

    A child's room with white routed furniture and a windowsill worktop · A work surface along the windowsill with cabinets and a tall unit

  2. FinishingFebruary 24, 20212 photos

    The junction of laminate flooring and wall with white skirting · The kitchen: an induction hob being fitted into the worktop

  3. CompletedFebruary 23, 20211 photo

    The living room: TV in a plasterboard recess above the marble fireplace surround

  4. Utilities and servicesFebruary 17, 20212 photos

    Heating pipes run along a room wall · An open concealed access hatch giving access to the services

  5. Utilities and servicesFebruary 15, 20217 photos

    Checking the water temperature with an infrared thermometer: 65.2 °C at the radiator · Measuring floor temperature with an infrared thermometer: 26.0 °C on the porcelain tile

  6. FinishingJanuary 11, 20211 photo

    A room with tile laid, a radiator and the duct boxed in

  7. CompletedJanuary 4, 20214 photos

    The hallway with a wavy laminate transition and decorative plaster · The hallway with finishing complete, recessed lighting and doors

  8. FinishingDecember 29, 202018 photos

    A white wall with three flush doors matching the finish · The entrance hall with concrete-effect plaster, laminate and a mirrored wardrobe

  9. Utilities and servicesDecember 28, 202010 photos

    Wiring and pipework in the bathroom · The hallway with marble-effect porcelain tile and parts of the future wardrobe

  10. First fixDecember 22, 20201 photo

    Laying floor tile in the hallway, continuing into the adjoining room

  11. FinishingDecember 17, 20201 photo

    A grey shower enclosure installed in the bathroom

  12. First fixDecember 7, 20201 photo

    Removing the old kitchen units and preparing the walls

  13. Utilities and servicesDecember 3, 20203 photos

    Electrical work in the bathroom · The entrance hall with painted walls and white doors fitted

  14. Utilities and servicesNovember 20, 20204 photos

    Water and heating pipes recessed into the bathroom wall · A group of sockets and switches installed in the bathroom

Documents

The contract, the estimate and the certificates live in the account, not in somebody's messenger. This project's archive holds 31 scanned documents — the documents themselves are closed in the demo.

  • Contract and annexesHidden
  • EstimateHidden
  • Certificates of completionHidden
  • Material specificationsHidden
  • As-built documentationHidden

Work in progress

Each stage is dates and frames from the site. These were shot for the job, not for a website, which is why some of them look exactly like a building site looks.

01

Demolition

April 2020 — July 20207 photos

Work completed

A living room after the plaster was chipped off, exposing the brickwork

April 3, 2020

A doorway between rooms stripped back to bare brick

April 3, 2020

A widened door opening with reveals built up in brick and mortar

April 10, 2020

The balcony with the old cladding partly removed

balcony · July 7, 2020

Debris removal: a tipper truck loaded with bags

The bathroom with tile stripped off and brickwork exposed

bathroom

Stripping tile and cladding in the bathroom

bathroom

02

Utilities and services

January 2020 — February 202130 photos

Work completed

The bathroom with the old toilet and towel rail before the rebuild

bathroom · January 28, 2020

Water supply and heating pipework run in the bathroom

bathroom · February 12, 2020

Trestles and tools in the living room during services installation

living room · February 14, 2020

An internal brick partition with the door opening completed

room · April 3, 2020

Carrier frame for the wall-hung toilet and chases cut for services

bathroom · May 20, 2020

Running electrical cable in a wall chase

May 20, 2020

Electrical work: cable bundles and groups of back boxes on the walls

May 20, 2020

Wiring and cable runs in the hallway

corridor · May 20, 2020

Marking out cable routes and installing wiring in a room

May 20, 2020

The completed water metering assembly with two sealed meters

bathroom · June 9, 2020

Plastered walls with layout marks and outlets for light fittings

June 9, 2020

A living room with services marked out, seen from the entrance

room · June 18, 2020

Ceiling marked out for downlights

living-bedroom · July 1, 2020

The bathroom with electrics and water pipes roughed in

bathroom · July 1, 2020

A room with a plasterboard ceiling and wiring in place

room · July 1, 2020

Installing water pipes and shut-off valves in the bathroom

bathroom · July 1, 2020

Running water supply pipes in the bathroom

bathroom · July 7, 2020

Electrical and plumbing rough-in in the bathroom

bathroom · September 7, 2020

The kitchen with electrics roughed in and tiling partly done

kitchen · October 26, 2020

Fitting sockets and switches onto the completed wiring

October 26, 2020

The hallway with services roughed in, seen from the entrance

corridor · October 26, 2020

Water and heating pipes recessed into the bathroom wall

bathroom · November 20, 2020

A group of sockets and switches installed in the bathroom

bathroom · November 20, 2020

Electrical work in the bathroom

bathroom · December 3, 2020

Wiring and pipework in the bathroom

bathroom · December 28, 2020

Checking the water temperature with an infrared thermometer: 65.2 °C at the radiator

February 15, 2021

Heating pipes run along a room wall

February 17, 2021

Junction boxes and cables recessed into the wall

The living room with electrics roughed in and heating pipes by the window

living room

Wiring layout marked out in a corner of the bathroom

bathroom

03

First fix

January 2020 — December 202030 photos

Work completed

The kitchen with electrics and plumbing roughed in

kitchen · January 28, 2020

The hallway ready for finishing, seen from the entrance

corridor · February 12, 2020

A room with new windows and a city view

living room · February 12, 2020

Walls after filling, with wiring run across the ceiling

room · February 19, 2020

Plastered room walls with a timber beam on the ceiling

room · February 19, 2020

An elongated room with a monolithic column and layout marks on the floor

February 19, 2020

Laying up new brick partitions to the setting-out lines

March 12, 2020

A completed red-brick partition with a steel lintel

March 31, 2020

The hallway with brick walls and services roughed in

corridor · April 3, 2020

A door opening in a brick wall after demolition

April 3, 2020

Hallway brickwork with setting-out marks applied

corridor · April 3, 2020

A brick wall partly skimmed with filler

April 10, 2020

The entrance hall: new partitions with openings, steel lintels, floor screed

hallway · April 10, 2020

The hallway with brick partitions, seen from the entrance

corridor · April 10, 2020

An opening in the wall with brickwork built up around the perimeter

room · April 10, 2020

A door opening in brickwork, front view

corridor · April 10, 2020

The suspended ceiling frame in the hallway, partly boarded out

hallway · June 18, 2020

Marking out and installing the plasterboard ceiling

July 1, 2020

A continuous moisture-resistant plasterboard ceiling in a room with a new window

July 1, 2020

The entrance hall: suspended ceiling installed, joints not yet filled

hallway · July 1, 2020

A bedroom with a two-level moisture-resistant plasterboard ceiling and cable for a light fitting

bedroom · July 1, 2020

The bathroom: one wall tiled, the adjacent one boarded in plasterboard

bathroom · September 30, 2020

The kitchen with units and appliances installed, seen from the room

kitchen · October 31, 2020

Removing the old kitchen units and preparing the walls

kitchen · December 7, 2020

Laying floor tile in the hallway, continuing into the adjoining room

corridor · December 22, 2020

A bathroom wall marked out and prepared for plastering

bathroom

A door opening with wiring roughed in, seen from the hallway

corridor

The bathroom with pipework run and battens ready for boarding

bathroom

A black entrance door in a levelled white room

room

A window opening with a radiator, walls prepared for finishing

room

04

Floor screed

1 photo

Work completed

Cement floor screed in the living room

living room

05

Plastering

January 2020 — November 20209 photos

Work completed

The kitchen with painted walls and tile, seen from the doorway

kitchen · January 28, 2020

The hallway with the ceiling prepared for plasterboard

corridor · July 1, 2020

Preparing the hallway ceiling and walls for finishing

corridor · July 1, 2020

The hallway: plastered walls, coving to the ceiling, lighting points

hallway · October 26, 2020

The entrance hall with a filled ceiling and coving around the perimeter

hallway · October 26, 2020

A living room wall after the plaster coat was applied

room · October 26, 2020

A bedroom with plastered walls and a new three-sash window

bedroom · October 26, 2020

A bedroom with a plasterboard ceiling and a recess for concealed lighting

bedroom · October 26, 2020

A room corner in plasterboard with filler applied

room · November 20, 2020

06

Finishing

January 2020 — February 202130 photos

Work completed

The living room with a plasterboard arch, olive walls and dark flooring

living room · January 28, 2020

A bedroom with a two-level ceiling, wallpaper and laminate flooring laid

bedroom · January 28, 2020

The kitchen-diner with a suspended ceiling and wall finishes partly done

January 28, 2020

A room after the walls and ceiling were painted, with coving fitted

September 3, 2020

The bathroom: one wall clad in marble-effect tile with a border

bathroom · September 7, 2020

Cornice moulding at the junction of the painted ceiling and beige wall

October 26, 2020

A room corner with coving, a pendant outlet and a new window reveal

bedroom · October 26, 2020

The entrance hall clad in light-wood-effect panelling, opening covered in film

hallway · October 26, 2020

A bathroom corner with large-format porcelain tile and a stretch ceiling

bathroom · October 26, 2020

A bedroom with a wallpapered feature wall and skirting fitted

bedroom · October 26, 2020

A bedroom with wallpaper, coving and a bank of three sockets

bedroom · October 26, 2020

A bathroom corner in onyx- and white-marble-effect porcelain tile

bathroom · October 26, 2020

The hallway with grey decorative plaster and a tiled floor

hallway · October 26, 2020

The bathroom with the clad portal and water outlets in recesses

bathroom · November 20, 2020

The entrance hall with painted walls and white doors fitted

hallway · December 3, 2020

The hallway with decorative plaster and a glass door in the opening

hallway · December 3, 2020

A grey shower enclosure installed in the bathroom

bathroom · December 17, 2020

The hallway with marble-effect porcelain tile and parts of the future wardrobe

hallway · December 28, 2020

The bathroom with the toilet, vanity unit and built-in bath installed

bathroom · December 28, 2020

A white wall with three flush doors matching the finish

December 29, 2020

The entrance hall with concrete-effect plaster, laminate and a mirrored wardrobe

hallway · December 29, 2020

A room with tile laid, a radiator and the duct boxed in

January 11, 2021

Measuring floor temperature with an infrared thermometer: 26.0 °C on the porcelain tile

February 15, 2021

Checking a radiator connection with an infrared thermometer: 64.7 °C

February 15, 2021

An open concealed access hatch giving access to the services

bathroom · February 17, 2021

The junction of laminate flooring and wall with white skirting

February 24, 2021

A spacious room with a tiled floor and built-in wardrobes

living room

The hall with plasterboard walls, tile and recessed LED lighting

An installed steel door with a closer, the gaps foamed

The hallway with doors fitted and access to the rooms

corridor

07

Furniture and fittings

December 2020 — February 202130 photos

Work completed

A bedroom with laminate flooring, a chandelier and furniture delivered

bedroom · December 28, 2020

A bedroom with a new window, radiator and chests of drawers still boxed

bedroom · December 28, 2020

A bedroom in beige tones with a classic chandelier and finished reveals

bedroom · December 28, 2020

A room during furniture delivery: cartons, bedside units, a chest of drawers

bedroom · December 28, 2020

A bedroom with a stretch ceiling and a wallpapered feature wall

bedroom · December 28, 2020

A child's room with built-in wardrobes, a worktop desk and a cabinet

child's room · December 29, 2020

A child's room with white and wenge fronts, cornice and downlights

child's room · December 29, 2020

A study with two rows of wall cabinets and socket banks above the worktop

study · December 29, 2020

The built-in desk with a cabinet and two-tone units, now installed

child's room · December 29, 2020

A child's room with furniture around the window and marble-pattern wall mural

child's room · December 29, 2020

A room with a desk built into the window recess and a pendant light

child's room · December 29, 2020

The kitchen: an induction hob being fitted into the worktop

kitchen · February 24, 2021

A child's room with white routed furniture and a windowsill worktop

child's room · February 25, 2021

A work surface along the windowsill with cabinets and a tall unit

child's room · February 25, 2021

A windowsill desk on a metal support with a radiator beneath the worktop

kitchen · February 25, 2021

The finished bedroom with a double bed and a wallpapered feature wall

bedroom · February 25, 2021

A bedroom with a wardrobe to ceiling height and wall lights by the bed

bedroom · February 25, 2021

A bedroom with an upholstered wall panel behind the bed and an air conditioner

bedroom · February 25, 2021

A bedroom with furniture delivered: bed, mattress still wrapped, wardrobe

bedroom · February 25, 2021

A bedroom with a chest of drawers, bedside units and a TV recess

bedroom · February 25, 2021

A built-in dressing room: shelves, drawers, hanging rails and lighting

hallway · February 25, 2021

A child's room with shelving units, a windowsill worktop and wall lights beside artwork

child's room

A desk integrated into the window recess with tall units on either side

child's room

View through glazed doors into a room with a built-in desk and cabinets

child's room

Wall cabinets and a desk worktop with a cabinet, shot from the hallway

child's room

The entrance hall with porcelain tile and a built-in wardrobe with over-cupboards

hallway

A room with laminate flooring, wallpaper on one wall and a chest of drawers delivered

living room

The kitchen with L-shaped units, splashback and task lighting

kitchen

A built-in dressing room in the entrance hall: corner shelves, drawers, rails

hallway

The dressing room with cabinet sections, shot from the doorway

hallway

08

Completed

January 2020 — February 202150 photos

Completed and handed over — Final photographs, after cleaning and handover.

A finished room with olive wallpaper, dark laminate flooring and an arch

living room · January 28, 2020

The bathroom with white tile, a lime-green inset and a whirlpool bath

bathroom · January 28, 2020

The living room with a panoramic window and a city view

living room · January 28, 2020

The entrance hall with dark laminate flooring, cornice and a lit recess

hallway · January 28, 2020

The living room with a two-level ceiling and a bar counter in decorative stone

living room · January 28, 2020

The living room with bay glazing and a curved plasterboard ceiling

living room · January 28, 2020

The hallway with a tiled floor and painted walls

corridor · January 28, 2020

The bathroom with marble-effect porcelain tile and a shadow-gap LED ceiling detail

bathroom · October 26, 2020

The finished bathroom with a built-in bath and lighting along the base of the wall

bathroom · December 28, 2020

An empty room with a stretch ceiling, ready for furniture

bedroom · December 28, 2020

A spacious living room with a decorative fireplace in a marble surround

living room · December 29, 2020

The living room with a corner fireplace, cornice and glazed doors

living room · December 29, 2020

The living room with a bay window and a marble fireplace surround

living room · December 29, 2020

The living room with the fireplace, light laminate flooring and finished walls

living room · December 29, 2020

A narrow hallway with white panelled doors and downlights

hallway · December 29, 2020

The bath surround with a mixer built into the worktop

bathroom · December 29, 2020

A bedroom with a built-in wardrobe, wallpaper and a feature wall

bedroom · December 29, 2020

The entrance hall with a full-height built-in wardrobe and a bench in the recess

hallway · December 29, 2020

The entrance hall with a wardrobe, mirrored inserts and wood-effect panelling

hallway · December 29, 2020

The glazed balcony with grey plaster, tile and a tall storage unit

balcony · December 29, 2020

The hallway with a wavy laminate transition and decorative plaster

hallway · January 4, 2021

The hallway with finishing complete, recessed lighting and doors

corridor · January 4, 2021

The entrance hall with a section of travertine-effect plaster and a moulded cornice

hallway · January 4, 2021

A brass wall light switched on, grazing the textured decorative plaster

hallway · January 4, 2021

A radiator with a Danfoss thermostatic head, infrared reading of 49.7 °C

February 15, 2021

Checking a radiator in a finished room: the infrared thermometer reads 28.0 °C

February 15, 2021

A reading of 63.2 °C on a radiator with a ball valve

February 15, 2021

Reading the connection of a panel radiator: 48.6 °C

February 15, 2021

The living room: TV in a plasterboard recess above the marble fireplace surround

living room · February 23, 2021

The finished bathroom: wall-hung toilet and the porcelain-to-laminate floor junction

bathroom · February 25, 2021

The dining area with marble-effect porcelain tile and a panelled feature wall

living room · February 25, 2021

The dining area with the table in place and finishing complete

February 25, 2021

The living room with a corner sofa, chest of drawers and double doors

living room · February 25, 2021

The living room with decorative wall finish, cornice and furniture delivered

living room · February 25, 2021

The living room with a stretch ceiling, fireplace and TV above the surround

living room · February 25, 2021

The bathroom with a glass-screened shower area and LED-lit recesses

bathroom · February 25, 2021

The hallway with pearlescent plaster on one of the walls

hallway · February 25, 2021

The entrance hall with a moulded cornice, deep skirting and wall lights

hallway · February 25, 2021

A guest bedroom with a sliding-door wardrobe and artwork behind the sofa

bedroom · February 25, 2021

A child's room with glazed display units flanking the window and a wall mural

child's room · February 25, 2021

The bathroom with a tiled bath surround and lighting beneath the units

bathroom · February 25, 2021

The bathroom with a built-in cupboard concealing the services

bathroom · February 25, 2021

A room with a stone-effect feature wall and a wall-mounted TV

living room

The entrance hall with a built-in wardrobe and a finished opening into the room

hallway

The empty living room with the fireplace, display cabinet and TV

living room

The kitchen-diner with access to the balcony and a decorative tile feature wall

kitchen

The kitchen with L-shaped units, marble-effect splashback and LED lighting

kitchen

The guest bathroom with a lit recess and a round mirror

bathroom

The lift lobby with grey porcelain tile and metal surrounds

The kitchen with grey marble-effect porcelain tile and access to the balcony

kitchen

Want the same account for your project?

We open the account on day one: the client sees stages, dates and photographs without waiting for a call from the site manager.

  • Access from the first day of work
  • Photo reports from site, not «all good»
  • Estimate, payments and balance in one place
+380 67 679 59 79

For example, +38 067 123 45 67

By sending this request you agree to our privacy policy.

Get a cost estimate