Demo accountCommercial · Kyiv, Pechersk

Studio renovation in Pechersk

Studio in Pechersk

A studio apartment in Kyiv's Pechersk district: work ran from June 2020 through April 2021. The scope covered demolition of brick partitions and reconfiguring the layout, building new walls in aerated concrete and brick, full rough-in electrical and plumbing runs, plaster, screed and final finishes. Part of the floor area was built out as residential units with bathrooms, part as commercial space with a loft character: exposed cable trays, track lighting, glass partitions and painted brick.

Commercial fit-out in Kyiv
Start
June 2020
Completed
April 2021
Photo record
10 months
Stages
8
Photos
131

Client

Name withheldKyiv, Pechersk
Project address
••••••••• St, ••
Type
Commercial
Rooms
11
Duration
10 months
Stages
8
Photo report
131
Documents
3

The client's name, photo and exact address are withheld. In their own account they see all of it.

Responsible for the project

Viacheslav MelnykViacheslav MelnykFounder of Archideal · general contractor

Runs the project himself: signs off stages, signs the certificates, answers the phone.

+380 67 679 59 79
Stages
8
Photos
131
Approvals
20
Documents
3

Stage schedule

8 stages · 131 photos

June 2020 — April 2021

Demolition
Utilities and services
First fix
Floor screed
Plastering
Finishing
Furniture and fittings
Completed

The bars are built from the dates the photographs were taken, not drawn by hand — which is why stages overlap. On a real site something is always being finished while the next trade has already started.

Estimate

In a working account this shows amounts per stage, payments made and the balance. In the demo they are hidden.

Demolition
CompletedAmount
4 ******₴amount hidden
Utilities and services
CompletedAmount
9 ******₴amount hidden
First fix
CompletedAmount
4 ******₴amount hidden
Floor screed
CompletedAmount
4 ******₴amount hidden
Plastering
CompletedAmount
3 ******₴amount hidden
Finishing
CompletedAmount
6 ******₴amount hidden
Furniture and fittings
CompletedAmount
9 ******₴amount hidden
Completed
CompletedAmount
3 ******₴amount hidden
Total7 *******₴amount hidden

The amounts are hidden because this is someone else's project. You will see your own in your estimate, not on a website.

Approvals

Every decision that affects the money or the look is logged as its own item. Until the client marks it approved, work on that item does not start.

18 approved · 2 returned

ItemApproved byDateStatus
Heating layoutUtilities and servicesClientJuly 5, 2020Approved
Floor and ceiling levelsFirst fixClientJuly 5, 2020Approved
Partition build-upFirst fixDesignerJuly 13, 2020Approved
Demolition plan and setting outDemolitionClientAugust 12, 2020Approved
Survey and floor planDemolitionEngineerAugust 12, 2020Approved
Plaster typePlasteringDesignerAugust 19, 2020Approved
Reveals and external cornersPlasteringEngineerSeptember 2, 2020Approved
Floor finishFinishingEngineerSeptember 4, 2020Approved
Doors and hardwareFinishingDesignerSeptember 23, 2020Approved
Wall colourFinishingClientSeptember 24, 2020Approved
Handover checklistCompletedEngineerSeptember 24, 2020Approved
Electrical layout and outletsUtilities and servicesClientSeptember 26, 2020Approved
Screed grade and thicknessFloor screedDesignerOctober 5, 2020Returned for revision
Screed grade and thicknessFloor screed · after revisionDesignerOctober 11, 2020Approved
Tile layoutFinishingEngineerNovember 1, 2020Approved
Water and drainage pointsUtilities and servicesEngineerNovember 4, 2020Approved
Kitchen drawingsFurniture and fittingsClientNovember 18, 2020Approved
Sanitaryware modelsFurniture and fittingsDesignerNovember 18, 2020Approved
Light fittingsFurniture and fittingsEngineerNovember 18, 2020Returned for revision
Light fittingsFurniture and fittings · after revisionEngineerNovember 24, 2020Approved

The approvals shown here are an example of how the mechanism works: the photographs do not record what was actually signed off on this project. Your account will carry your own history.

On site

  • Site managerdaily supervision and photo reports
  • Project managerestimate, schedule, contact with the client
  • Engineerdrawings and details

Rooms

How many frames each part of the project accounts for.

  • bathroom29
  • living room9
  • hallway6
  • room5
  • facade4
  • utility room2
  • corridor2
  • living-bedroom1
  • balcony1
  • office1
  • bedroom1

Site log

Every day the site was photographed. The dates are real — read from the files, not typed in.

16 days photographed

  1. CompletedApril 1, 20212 photos

    Modern office with workstations and built-in furniture · Office space with furniture and equipment in place

  2. Utilities and servicesMarch 31, 202111 photos

    Bathroom ceiling with electrical and service runs · Perforated cable trays and ductwork under the painted ceiling

  3. Utilities and servicesNovember 18, 202044 photos

    Wiring runs and wall lights being fitted in the living area · The plant room with equipment installed and cables brought in

  4. FinishingNovember 3, 20203 photos

    Water heater in a recess above terracotta tiling, with a ventilation outlet alongside · Entrance door with its hardware and electrical fittings installed alongside

  5. Utilities and servicesOctober 5, 202011 photos

    Electrical runs in place and the bathroom walls being prepared · Service penetrations in the ceiling for routing the utilities

  6. Utilities and servicesSeptember 28, 20203 photos

    Installing cable trunking and services in the bathroom · A recessed consumer unit with three rows of breakers and an RCD

  7. CompletedSeptember 11, 20201 photo

    Rainscreen façade panels and balconies with metal railings

  8. FinishingSeptember 10, 20203 photos

    Bathroom with light tiling, a wall-hung WC and a concrete basin · Completed bathroom tiling and a basin on a white frame

  9. Utilities and servicesSeptember 3, 20205 photos

    Cables and back boxes prepared before the fittings go in · The soil stack in a recess in the aerated concrete wall, with a double socket alongside

  10. CompletedSeptember 1, 20201 photo

    Ventilated façade with orange accents and the entrance with signage

  11. Utilities and servicesAugust 31, 20204 photos

    Aerated concrete partitions in the living room, cabling run across the concrete ceiling · An aerated concrete pier with a niche, some walls already filled

  12. DemolitionAugust 12, 202015 photos

    A room after the wall came down, with the brickwork left exposed · A wall stripped of its old finishes next to the window

  13. Utilities and servicesAugust 7, 20202 photos

    Partition framing: steel studs next to the brickwork · Cable runs across the ceiling with a junction box

  14. CompletedJuly 6, 20202 photos

    Façade of the residential complex with rainscreen panels and a landscaped courtyard · Façade with ground-floor commercial units and shopfront glazing

Documents

The contract, the estimate and the certificates live in the account, not in somebody's messenger. This project's archive holds 3 scanned documents — the documents themselves are closed in the demo.

  • Contract and annexesHidden
  • EstimateHidden
  • Certificates of completionHidden
  • Material specificationsHidden
  • As-built documentationHidden

Work in progress

Each stage is dates and frames from the site. These were shot for the job, not for a website, which is why some of them look exactly like a building site looks.

01

Demolition

August 20205 photos

Work completed

A room after the wall came down, with the brickwork left exposed

room · August 12, 2020

A wall stripped of its old finishes next to the window

room · August 12, 2020

Brickwork after the plaster was chipped off

room

Dismantled brick piers with a pile of construction debris on the floor

Cutting an opening through the brickwork, with a cable and junction box hanging above

02

Utilities and services

June 2020 — March 202129 photos

Work completed

The steel entrance door installed, with vertical cable runs in flexible conduit

hallway · June 22, 2020

Wiring run in plastic surface trunking along the brick wall

utility room · June 22, 2020

Partition framing: steel studs next to the brickwork

August 7, 2020

Cable runs across the ceiling with a junction box

August 7, 2020

A bathroom at the stage of wiring installation, with a temporary light fitting

bathroom · August 12, 2020

A junction box with cables brought out in the bathroom

bathroom · August 12, 2020

The main room with electrical points brought out and materials stacked up

August 12, 2020

Aerated concrete partitions in the living room, cabling run across the concrete ceiling

living room · August 31, 2020

Cables and back boxes prepared before the fittings go in

September 3, 2020

The soil stack in a recess in the aerated concrete wall, with a double socket alongside

bathroom · September 3, 2020

Ceiling marked out for the future electrical routes

September 3, 2020

The bathroom with electrical and water supply runs in place

bathroom · September 3, 2020

Installing cable trunking and services in the bathroom

bathroom · September 28, 2020

A recessed consumer unit with three rows of breakers and an RCD

hallway · September 28, 2020

Electrical runs in place and the bathroom walls being prepared

bathroom · October 5, 2020

Service penetrations in the ceiling for routing the utilities

October 5, 2020

Trunking with cable runs along the ceiling

October 5, 2020

Ceiling cable runs in the corridor

corridor · October 5, 2020

Bathroom wall with wiring brought out for sockets

bathroom · October 5, 2020

Electrics and pipework in the bathroom before it is closed up

bathroom · October 5, 2020

Installing the shower area in the bathroom

bathroom · October 5, 2020

Wiring runs and wall lights being fitted in the living area

living-bedroom · November 18, 2020

The plant room with equipment installed and cables brought in

utility room · November 18, 2020

Running services in the bathroom

bathroom · November 18, 2020

Bathroom ceiling with electrical and service runs

bathroom · March 31, 2021

Perforated cable trays and ductwork under the painted ceiling

March 31, 2021

Bundles of cable in conduit set into a floor recess along the wall

Cables brought out on the wall for a wall-mounted TV

room

Electrical runs with red and blue cable

03

First fix

June 2020 — September 202018 photos

Work completed

A room with a brick wall, a window and layout marks on the floor

June 22, 2020

The living room with floor-to-ceiling glazing and a levelled concrete screed

living room · June 22, 2020

Brick partitions, screed and cables brought out with back boxes

June 22, 2020

Wiring run along the brick wall

August 12, 2020

A space at the marking-out and preparation stage before finishing

August 12, 2020

A room with balcony access at rough-in stage

living room · August 12, 2020

Bathroom: walls prepared for plaster and services run in

bathroom · August 12, 2020

Hallway walls prepared for finishing, with electrics brought out

hallway · August 12, 2020

Corridor with door openings cut through, viewed along the wall

corridor · August 12, 2020

Suspended ceiling framing and a filled column in the living room

living room · August 12, 2020

Full-height glazing unit with balcony door, cement screed across the floor

August 12, 2020

A corner space with glazing and the heating radiators connected

living room · August 12, 2020

Bathroom walls after priming, ready for tiling

bathroom · September 3, 2020

Laying an internal partition in ceramic brick, the wall built up halfway

uPVC windows installed with double glazing

Balcony door set in brown profile with a radiator under the sill

living room

Living room with a concrete floor, windows and walls already painted

living room

Glazing with access to the loggia, radiator still in its protective wrap

balcony

04

Floor screed

October 20201 photo

Work completed

Concrete floor screed poured between the cast-in-place columns

room · October 5, 2020

05

Plastering

August 2020 — October 20202 photos

Work completed

Plastered walls and a pier-column in the middle of the room

August 12, 2020

Bathroom ceiling and walls levelled with plasterboard

bathroom · October 5, 2020

06

Finishing

August 2020 — March 202124 photos

Work completed

An aerated concrete pier with a niche, some walls already filled

August 31, 2020

Beige glazed tiles laid in an offset pattern, joints grouted

bathroom · August 31, 2020

The junction of large-format porcelain tile and laminate in the hall

hallway · August 31, 2020

Bathroom with light tiling, a wall-hung WC and a concrete basin

bathroom · September 10, 2020

Completed bathroom tiling and a basin on a white frame

bathroom · September 10, 2020

A storage water heater under the bathroom ceiling with connections made

bathroom · September 10, 2020

Plasterboard ceiling with a shadow gap and a track lighting system

September 28, 2020

Painted walls and ceiling, a track light and framing for the glazing

October 5, 2020

Glass partition on a block parapet with pink LED lighting

October 5, 2020

Water heater in a recess above terracotta tiling, with a ventilation outlet alongside

bathroom · November 3, 2020

A decorative toggle switch on glossy metro tile

November 18, 2020

Wall lights on a white wall with a patch of whitewashed brick

November 18, 2020

Two pendant lights against a textured concrete wall

November 18, 2020

A room with an air conditioner, a mint-coloured wardrobe and full-height glazing

living room · November 18, 2020

A low block parapet with a glass screen and pink lighting

November 18, 2020

Loft-style hall: whitewashed brick, glass partition, track lighting

November 18, 2020

Hallway with the entrance door and marble-effect porcelain tile

hallway · November 18, 2020

Corridor with a glass partition and exposed cable trays

November 18, 2020

A decorative 3D panel with concealed LED lighting

November 18, 2020

A room with skirting, track lighting and a light-toned floor finish

living room · November 18, 2020

A light fitting mounted on the painted ceiling

March 31, 2021

Office space with stretch ceilings and partitions

March 31, 2021

A glazed partition in aluminium profile with frosted panels

Glass office partition with blinds

office

07

Furniture and fittings

November 20202 photos

Work completed

Corner reception desk with white 3D panels and lighting along the countertop

November 18, 2020

Vanity unit with a basin; a macerator pump visible behind the open door

bathroom · November 18, 2020

08

Completed

June 2020 — April 202150 photos

Completed and handed over — Final photographs, after cleaning and handover.

Finished corridor: two-level ceiling with lighting, porcelain tile flooring

hallway · June 22, 2020

Loft-style salon hall: whitewashed brick, pendant lamps, dark floor

July 3, 2020

Office space with furniture and the wall finishes complete

July 3, 2020

Salon with decorative brick, laminate flooring and a host of pendant lights

July 3, 2020

Façade of the residential complex with rainscreen panels and a landscaped courtyard

facade · July 6, 2020

Façade with ground-floor commercial units and shopfront glazing

facade · July 6, 2020

Ventilated façade with orange accents and the entrance with signage

facade · September 1, 2020

Rainscreen façade panels and balconies with metal railings

facade · September 11, 2020

Entrance door with its hardware and electrical fittings installed alongside

November 3, 2020

Bathroom with a bidet and a suspended ceiling, tiling complete

bathroom · November 3, 2020

Reception with soft quilted panels, an LED outline and a neon sign

November 18, 2020

Poured floor, glass partitions and a counter with neon lighting

November 18, 2020

A bright hall with slatted panels and lines of track lights

November 18, 2020

A wall of vertical slatted panels in a powder shade, with a heavy curtain

November 18, 2020

Full-height fitted cupboards, open trays with track lighting under the ceiling

November 18, 2020

Make-up area with mirrored tables and lilac lighting

November 18, 2020

Corridor with a glass partition, cable trays and concealed lighting

November 18, 2020

Guest bathroom with a wall-hung WC and a pedestal basin

bathroom · November 18, 2020

A countertop basin on a white metal frame with a wall-mounted mixer

bathroom · November 18, 2020

Bathroom with a round backlit mirror and a vertical LED line

bathroom · November 18, 2020

Pink-lilac metro tile, a pedestal basin and an illuminated wall feature

bathroom · November 18, 2020

Office with frosted glass partitions and an exposed concrete ceiling

November 18, 2020

Zoning in frosted glass with metal hardware, air conditioner installed

November 18, 2020

Wall-hung vanity with a countertop basin against whitewashed brick

bathroom · November 18, 2020

A slatted panel wall with concealed doors, and heavy curtains

November 18, 2020

Salon with display cases, a ring light and a patch of exposed masonry

November 18, 2020

Lounge area with full-height glazing, a ring light and whitewashed brick

November 18, 2020

A glass partition separates the work area; light-toned poured floor

November 18, 2020

Frameless glass partition with swing doors in front of an office

November 18, 2020

Work area behind glass partitions on point fixings

November 18, 2020

A glass partition in a slim aluminium profile between the office and the corridor

November 18, 2020

Corridor with concealed doors, a cable tray and track lighting under the ceiling

November 18, 2020

Retail floor with metal shelving units and LED shelf lighting

November 18, 2020

Lit display cases, exposed ductwork and trays above the sales floor

November 18, 2020

Mirrored workstations and a desk with a decorative button-tufted wall

November 18, 2020

Acoustic panels on the wall, a cable tray and track along the ceiling

November 18, 2020

A long counter with a row of mirrors in metal frames and sockets in the worktop

November 18, 2020

A corner with a water cooler and an armchair by a curtained glass partition

November 18, 2020

Perforated trays with surface-mounted lights, glass with a neon sign

November 18, 2020

Glass partition with a logo and a make-up area with a lit counter

March 31, 2021

Frameless glass partitions, white display cases and a neon sign

March 31, 2021

Office with fitted cupboards and a glass partition with lighting

March 31, 2021

Reception desk with a quilted 3D panel and a pink LED outline

March 31, 2021

Guest bathroom with an LED-outlined mirror and a concealed cistern

bathroom · March 31, 2021

Oval backlit mirror and a cylindrical vanity with a basin

bathroom · March 31, 2021

A monolithic half-cylinder vanity beneath a countertop basin, with a round mirror

bathroom · March 31, 2021

Modern office with workstations and built-in furniture

April 1, 2021

Office space with furniture and equipment in place

April 1, 2021

Built-in desk on a plinth with decorative tile and a neon figure

bedroom

Reception desk with relief panels, neon and an exposed concrete ceiling

Want the same account for your project?

We open the account on day one: the client sees stages, dates and photographs without waiting for a call from the site manager.

  • Access from the first day of work
  • Photo reports from site, not «all good»
  • Estimate, payments and balance in one place
+380 67 679 59 79

For example, +38 067 123 45 67

By sending this request you agree to our privacy policy.

Get a cost estimate