Two-room apartment renovation on Skoropadskoho

Two-room apartment on Skoropadskoho

A two-room apartment in a pre-war building on Skoropadskoho Street in central Kyiv. Work ran from March 2019 to March 2021: complete strip-out of the old finishes down to the brickwork, demolition of partitions and widening of openings, all-new services — water metering assembly, pressure reducers, consumer unit with modular breakers, screeds, plaster, and a balcony lined with plasterboard over insulation. The finishes include white decorative brick, black-and-white checkerboard tile, deep blue painted walls, and metro tile in the kitchen and bathroom.

Turnkey apartment renovation in Kyiv
Start
March 2019
Completed
March 2021
Photo record
24 months
Stages
8
Photos
125

Client

Name withheldKyiv, city centre
Project address
••••••••• St, ••
Type
Apartment
Rooms
9
Duration
24 months
Stages
8
Photo report
125
Documents
2

The client's name, photo and exact address are withheld. In their own account they see all of it.

Responsible for the project

Viacheslav MelnykViacheslav MelnykFounder of Archideal · general contractor

Runs the project himself: signs off stages, signs the certificates, answers the phone.

+380 67 679 59 79
Stages
8
Photos
125
Approvals
20
Documents
2

Stage schedule

8 stages · 125 photos

March 2019 — March 2021

Demolition
Utilities and services
First fix
Floor screed
Plastering
Finishing
Furniture and fittings
Completed

The bars are built from the dates the photographs were taken, not drawn by hand — which is why stages overlap. On a real site something is always being finished while the next trade has already started.

Estimate

In a working account this shows amounts per stage, payments made and the balance. In the demo they are hidden.

Demolition
CompletedAmount
4 ******₴amount hidden
Utilities and services
CompletedAmount
9 ******₴amount hidden
First fix
CompletedAmount
4 ******₴amount hidden
Floor screed
CompletedAmount
4 ******₴amount hidden
Plastering
CompletedAmount
3 ******₴amount hidden
Finishing
CompletedAmount
6 ******₴amount hidden
Furniture and fittings
CompletedAmount
9 ******₴amount hidden
Completed
CompletedAmount
3 ******₴amount hidden
Total4 *******₴amount hidden

The amounts are hidden because this is someone else's project. You will see your own in your estimate, not on a website.

Approvals

Every decision that affects the money or the look is logged as its own item. Until the client marks it approved, work on that item does not start.

18 approved · 2 returned

ItemApproved byDateStatus
Demolition plan and setting outDemolitionClientApril 11, 2019Approved
Survey and floor planDemolitionClientApril 17, 2019Approved
Heating layoutUtilities and servicesEngineerApril 18, 2019Approved
Water and drainage pointsUtilities and servicesClientMay 13, 2019Approved
Floor finishFinishingDesignerMay 24, 2019Approved
Screed grade and thicknessFloor screedEngineerMay 27, 2019Approved
Reveals and external cornersPlasteringDesignerMay 29, 2019Approved
Electrical layout and outletsUtilities and servicesDesignerJune 22, 2019Approved
Plaster typePlasteringEngineerJuly 8, 2019Approved
Tile layoutFinishingDesignerDecember 7, 2019Approved
Wall colourFinishingDesignerDecember 30, 2019Returned for revision
Wall colourFinishing · after revisionDesignerJanuary 5, 2020Approved
Doors and hardwareFinishingEngineerJanuary 10, 2020Approved
Partition build-upFirst fixEngineerJanuary 20, 2020Approved
Floor and ceiling levelsFirst fixDesignerFebruary 20, 2020Approved
Handover checklistCompletedDesignerJune 21, 2020Returned for revision
Handover checklistCompleted · after revisionDesignerJune 27, 2020Approved
Kitchen drawingsFurniture and fittingsClientFebruary 19, 2021Approved
Light fittingsFurniture and fittingsDesignerMarch 2, 2021Approved
Sanitaryware modelsFurniture and fittingsEngineerMarch 3, 2021Approved

The approvals shown here are an example of how the mechanism works: the photographs do not record what was actually signed off on this project. Your account will carry your own history.

On site

  • Site managerdaily supervision and photo reports
  • Project managerestimate, schedule, contact with the client
  • Engineerdrawings and details

Rooms

How many frames each part of the project accounts for.

  • bathroom23
  • room13
  • balcony13
  • living room12
  • hallway10
  • kitchen9
  • corridor4
  • bedroom2
  • facade1

Site log

Every day the site was photographed. The dates are real — read from the files, not typed in.

32 days photographed

  1. Furniture and fittingsMarch 18, 20216 photos

    Bedroom after renovation: stretch ceiling, blue wall, white brick · Finished kitchen: blue units, checkerboard floor, table by the window

  2. First fixMarch 16, 20211 photo

    Laying the floor finish with transitions between rooms

  3. CompletedMarch 15, 20211 photo

    White worktop with a built-in gas hob and metro tile splashback

  4. FinishingMarch 14, 20211 photo

    Washbasin area: vanity unit, mirror, blue wall and white brick

  5. Furniture and fittingsFebruary 19, 20212 photos

    Metro tile splashback with LED lighting over the worktop · Kitchen with a stretch ceiling and integrated lighting

  6. FinishingOctober 23, 20201 photo

    Laying the bathroom floor tile

  7. FinishingOctober 17, 20203 photos

    Living room with plastic windows and balcony door · Room with balcony access after finishing: grey walls, checkerboard tile

  8. FinishingDecember 27, 20191 photo

    Indoor air conditioning unit on a deep blue wall

  9. Utilities and servicesDecember 11, 20191 photo

    Assembled apartment panel: meter, main breaker, MCBs on the DIN rail

  10. FinishingDecember 10, 20192 photos

    Entrance hall: white brick, blue wall, corners masked with tape · Finished balcony: white decorative brick, cornice, neat reveals

  11. FinishingDecember 6, 20191 photo

    Metal consumer unit enclosure mounted on the deep blue wall

  12. FinishingDecember 2, 20194 photos

    Deep blue hallway with the door set and architraves fitted · Fitting the door set and architraves in the blue hallway

  13. First fixNovember 13, 20196 photos

    The bathroom being lined with plasterboard · Detail of a wall in decorative brick

  14. FinishingOctober 21, 20192 photos

    Toilet installed along with the bathroom services · Internal corner: decorative brick meeting a filled wall

Documents

The contract, the estimate and the certificates live in the account, not in somebody's messenger. This project's archive holds 2 scanned documents — the documents themselves are closed in the demo.

  • Contract and annexesHidden
  • EstimateHidden
  • Certificates of completionHidden
  • Material specificationsHidden
  • As-built documentationHidden

Work in progress

Each stage is dates and frames from the site. These were shot for the job, not for a website, which is why some of them look exactly like a building site looks.

01

Demolition

April 2019 — June 201916 photos

Work completed

Stripping the old finish from a wall in the living room

room · April 8, 2019

The bathroom after the wall finishes and floor were stripped out

bathroom · April 8, 2019

The apartment mid strip-out, the floor buried in plaster rubble

April 8, 2019

The bathroom during removal of the old renovation

bathroom · April 8, 2019

Living room with plaster knocked off and a partition partly demolished

living room · April 8, 2019

View from the entrance into the room with the walls taken down

living room · April 18, 2019

Exposed brickwork and a new polypropylene riser in the corner

April 18, 2019

Bathroom stripped to brick, with old steel pipework and the fixtures removed

bathroom · April 18, 2019

Plastic soil pipe in the corner, ceiling already plastered

April 19, 2019

Spacious room with walls stripped to brick and the floor down to concrete

May 25, 2019

Walls cleaned back to brick and cinder block, a new opening cut on the right

living room · May 25, 2019

New uPVC balcony door and window set installed among bare walls

May 25, 2019

The main room with brick walls during the strip-out

May 25, 2019

Measuring the widened opening between rooms with a tape

May 25, 2019

Taking measurements along a wall of cleaned brickwork

room · May 25, 2019

A wide opening cut through between the entrance hall and the room

hallway · June 18, 2019

02

Utilities and services

April 2019 — December 201930 photos

Work completed

Water supply and heating pipework in the bathroom

bathroom · April 4, 2019

The bathroom after strip-out with the services run in

bathroom · April 18, 2019

Plumbing and electrical runs in the bathroom

bathroom · May 25, 2019

Living room with bare walls ready for finishing

room · May 25, 2019

Wall-hung toilet carrier frame, manifold with pressure gauges, aerated block work

bathroom · June 3, 2019

Toilet pan installed among the bathroom services

bathroom · June 3, 2019

Running electrical cable in wall chases

June 14, 2019

Ceiling with cabling run out to the light points

room · June 18, 2019

Sliding unit fitted to the window, seen from inside

room · June 18, 2019

The room at the first-fix electrical and plumbing stage

room · June 18, 2019

Cable runs in the wall chases

June 18, 2019

Wiring and pipework beneath the ceiling

June 18, 2019

Electrical and water runs in the bathroom

bathroom · June 18, 2019

Balcony with a timber frame and services run in

facade · June 18, 2019

Installing wiring and underfloor heating loops

July 11, 2019

Ceiling wiring in the room, looking upward

room · July 11, 2019

Water metering assembly with two meters, a filter and pressure gauges

bathroom · July 11, 2019

Consumer unit with wiring and cable trunking

July 15, 2019

Electrical runs in the wall chases

July 15, 2019

Room with a brick wall and the wiring run in

room · August 20, 2019

Installing the ceiling profile for plasterboard in the hallway

corridor · August 28, 2019

Ceiling services with plasterboard lining started

August 28, 2019

Assembled apartment panel: meter, main breaker, MCBs on the DIN rail

hallway · December 11, 2019

Water inlet assembly with two pressure reducers and a strainer

Electrical runs protected under plastic sheeting

Marking out the electrical points on the bathroom wall

bathroom

Living room with the wiring run in, seen from the entrance

living room

Balcony lined with plasterboard and marked out for services

balcony

Heating pipework and power supply in the basement

Panel recessed into a niche with MCBs and an RCD, walls still bare

hallway

03

First fix

March 2019 — March 202130 photos

Work completed

The living room with its old wallpaper before work began

living room · March 6, 2019

Doorway in a brick wall with a timber frame

bathroom · March 6, 2019

Hallway with the floor being prepared, seen from the front door

corridor · March 6, 2019

Wall with the plaster removed, floor covered in construction dust

April 18, 2019

Hallway with brick walls and the entrance door

corridor · April 18, 2019

The old ceiling light before removal

living room · April 23, 2019

Spacious room with brick walls and two windows

living room · May 8, 2019

New balcony windows, Plastolit sills, reveals insulated with mineral wool

balcony · May 25, 2019

Measuring and marking out on the fresh floor screed

room · May 25, 2019

Checking the substrate for flatness with a level and tape, an aerated block alongside

May 25, 2019

Kitchen with a brick wall, unfinished ceiling and wiring

kitchen · May 29, 2019

Brick wall with windows, sills and setting-out marks

June 7, 2019

Balcony lined with moisture-resistant plasterboard, floor screeded

balcony · June 14, 2019

Narrow loggia: parapet boarded out, joints foamed, ceiling painted

balcony · June 14, 2019

Entrance hall wall with wiring after the plaster was removed

hallway · June 14, 2019

Bedroom: plasterboard partition with cables and socket boxes brought out

bedroom · June 18, 2019

Installing the metal framing and boards in the bathroom

bathroom · June 18, 2019

Laying floor finish in the corner of the room

July 11, 2019

Plasterboard wall with the joints filled, cables across the ceiling

July 11, 2019

Balcony: new windows, foamed joints, walls and ceiling painted green

balcony · July 11, 2019

Wall lined with MR plasterboard, joints filled, socket boxes fitted

July 15, 2019

White ceramic tile in its factory packaging

July 25, 2019

Living room with floor preparation and the wiring run in

room · August 20, 2019

The bathroom being lined with plasterboard

bathroom · November 13, 2019

Laying the floor finish with transitions between rooms

corridor · March 16, 2021

Balcony window with the sill being fitted and reveals finished

balcony

New plastic balcony windows with perforated plaster beads

balcony

Balcony walls in MR plasterboard behind a vapour barrier, floor screeded

balcony

Metal framing studs and services run in the room

room

Plasterboard bathroom ceiling with setting-out marks

bathroom

04

Floor screed

May 20193 photos

Work completed

Concrete floor screed marked out for the screed rails

May 25, 2019

Checking the screed for flatness with a straightedge and laser distance meter

May 25, 2019

Screed on the balcony, parapet clad in profiled sheeting

balcony · May 29, 2019

05

Plastering

May 2019 — November 20194 photos

Work completed

Plastered ceiling with the wiring run out

room · May 25, 2019

Aerated concrete partition with an opening, walls in gypsum plaster

June 7, 2019

Checking the plastered wall for plumb with a spirit level

June 14, 2019

Detail of a wall in decorative brick

November 13, 2019

06

Finishing

March 2019 — March 202130 photos

Work completed

Before and after: the old room and the finished living room

living room · March 6, 2019

Balcony with steel radiators and plastic windows

balcony · May 25, 2019

Balcony glazing: windows with a top-hung opening sash, joints foamed

balcony · May 25, 2019

Four-gang Legrand socket box in a decorative brick wall

August 20, 2019

Long wall almost entirely clad in white gypsum brick

August 20, 2019

Toilet installed along with the bathroom services

bathroom · October 21, 2019

Internal corner: decorative brick meeting a filled wall

October 21, 2019

Living room nearing completion: ceiling with spotlights, checkerboard tile, white brick

living room · November 13, 2019

Room corner with decorative brick and the ceiling cornice fitted

November 13, 2019

Entrance hall: checkerboard tile, white brick, spotlights and cornice

hallway · November 13, 2019

Hallway with the doors, cornice and downlights installed

hallway · November 13, 2019

Deep blue hallway with the door set and architraves fitted

hallway · December 2, 2019

Fitting the door set and architraves in the blue hallway

hallway · December 2, 2019

Two-level plasterboard ceiling with moulded cornice and a blue wall

December 2, 2019

Metal consumer unit enclosure mounted on the deep blue wall

December 6, 2019

Entrance hall: white brick, blue wall, corners masked with tape

hallway · December 10, 2019

Indoor air conditioning unit on a deep blue wall

December 27, 2019

Living room with plastic windows and balcony door

living room · October 17, 2020

Room with balcony access after finishing: grey walls, checkerboard tile

living room · October 17, 2020

Laying the bathroom floor tile

bathroom · October 23, 2020

Washbasin area: vanity unit, mirror, blue wall and white brick

bathroom · March 14, 2021

Kitchen wall in white metro tile with electrical and water outlets

kitchen

Room with the ceramic floor laid in a checkerboard pattern

room

Checkerboard floor complete, walls still unfinished

Bathroom with a plinth for the shower tray and outlets for the mixer

bathroom

Plasterboard balcony ceiling marked out for light fittings

balcony

Kitchen: metro tile with grey grout, ceiling still unfinished

kitchen

White metro tile with outlets for lighting and a ventilation duct

bathroom

Shower tray in the corner, walls in textured white tile

bathroom

Vestibule with checkerboard tile and an unfinished brick pier

hallway

07

Furniture and fittings

February 2021 — March 20212 photos

Work completed

Metro tile splashback with LED lighting over the worktop

kitchen · February 19, 2021

Bedroom after renovation: stretch ceiling, blue wall, white brick

bedroom · March 18, 2021

08

Completed

December 2019 — March 202110 photos

Completed and handed over — Final photographs, after cleaning and handover.

Corner of the finished interior: two-level ceiling, cornice, square downlights

December 2, 2019

Finished balcony: white decorative brick, cornice, neat reveals

balcony · December 10, 2019

Completed living room with white brick, a sofa and air conditioning

living room · October 17, 2020

Kitchen with a stretch ceiling and integrated lighting

kitchen · February 19, 2021

White worktop with a built-in gas hob and metro tile splashback

kitchen · March 15, 2021

Finished kitchen: blue units, checkerboard floor, table by the window

kitchen · March 18, 2021

Completed bathroom: shower enclosure, wall-hung toilet, vanity with mirror

bathroom · March 18, 2021

Finished kitchen in blue and white with L-shaped units

kitchen · March 18, 2021

L-shaped units with blue fronts, ceiling with mouldings and downlights

kitchen · March 18, 2021

Finished light bathroom with a shower enclosure and backlit mirror

bathroom · March 18, 2021

Want the same account for your project?

We open the account on day one: the client sees stages, dates and photographs without waiting for a call from the site manager.

  • Access from the first day of work
  • Photo reports from site, not «all good»