House construction in Demydiv

House in Demydiv

A single-storey timber-frame house in Demydiv, Kyiv region: from setting out the foundation and erecting the frame through to full interior finishing, furnishing and site landscaping. The complete cycle was carried out — mineral wool insulation, electrics with distribution boards and backup power from an inverter with battery storage, water supply, electric underfloor heating, timber planken cladding, a metal tile roof, paving and fencing. Work ran from May 2025 to March 2026.

Private house construction in Kyiv and the region
Start
May 2025
Completed
March 2026
Photo record
10 months
Stages
8
Photos
158

Client

Name withheldDemydiv, Kyiv region
Project address
••••••••• St, ••
Type
House
Rooms
16
Duration
10 months
Stages
8
Photo report
158
Documents
26

The client's name, photo and exact address are withheld. In their own account they see all of it.

Responsible for the project

Viacheslav MelnykViacheslav MelnykFounder of Archideal · general contractor

Runs the project himself: signs off stages, signs the certificates, answers the phone.

+380 67 679 59 79

The account as the owner saw it on November 21, 2025: some stages closed, one under way, the rest ahead. Nothing has been altered — anything photographed later is simply hidden.

Stages
8
Photos
104 / 158
Approvals
17
Documents
26

Stage schedule

As of November 21, 2025 · 104 of 158 photos

May 2025 — March 2026

Site preparation
Utilities and services
First fix
Floor screed
Plastering
Finishing
Furniture and fittings
Completed

The bars are built from the dates the photographs were taken, not drawn by hand — which is why stages overlap. On a real site something is always being finished while the next trade has already started.

Estimate

In a working account this shows amounts per stage, payments made and the balance. In the demo they are hidden.

Site preparation
In progressAmount
1 ******₴amount hidden
Utilities and services
In progressAmount
9 ******₴amount hidden
First fix
In progressAmount
4 ******₴amount hidden
Floor screed
CompletedAmount
4 ******₴amount hidden
Plastering
CompletedAmount
3 ******₴amount hidden
Finishing
In progressAmount
6 ******₴amount hidden
Furniture and fittings
In progressAmount
9 ******₴amount hidden
Completed
In progressAmount
3 ******₴amount hidden
Total6 *******₴amount hidden

The amounts are hidden because this is someone else's project. You will see your own in your estimate, not on a website.

Approvals

Every decision that affects the money or the look is logged as its own item. Until the client marks it approved, work on that item does not start.

16 approved · 1 returned

ItemApproved byDateStatus
Water and drainage pointsUtilities and servicesEngineerJune 3, 2025Approved
Electrical layout and outletsUtilities and servicesClientJune 18, 2025Approved
Floor and ceiling levelsFirst fixClientJune 27, 2025Approved
Demolition plan and setting outSite preparationClientJuly 23, 2025Approved
Heating layoutUtilities and servicesClientAugust 1, 2025Approved
Partition build-upFirst fixEngineerAugust 18, 2025Approved
Survey and floor planSite preparationDesignerAugust 24, 2025Approved
Plaster typePlasteringEngineerAugust 31, 2025Returned for revision
Reveals and external cornersPlasteringClientSeptember 1, 2025Approved
Plaster typePlastering · after revisionEngineerSeptember 6, 2025Approved
Floor finishFinishingClientSeptember 17, 2025Approved
Wall colourFinishingClientSeptember 20, 2025Approved
Screed grade and thicknessFloor screedEngineerNovember 4, 2025Approved
Light fittingsFurniture and fittingsClientNovember 7, 2025Approved
Sanitaryware modelsFurniture and fittingsDesignerNovember 8, 2025Approved
Doors and hardwareFinishingDesignerNovember 11, 2025Approved
Kitchen drawingsFurniture and fittingsEngineerNovember 13, 2025Approved

The approvals shown here are an example of how the mechanism works: the photographs do not record what was actually signed off on this project. Your account will carry your own history.

On site

  • Site managerdaily supervision and photo reports
  • Project managerestimate, schedule, contact with the client
  • Engineerdrawings and details

Rooms

How many frames each part of the project accounts for.

  • bedroom21
  • facade21
  • bathroom18
  • living room18
  • kitchen13
  • plot10
  • hallway9
  • balcony3
  • room2
  • entrance2
  • grounds1
  • outdoors1
  • terrace1
  • utility room1
  • corridor1
  • living-bedroom1

Site log

Every day the site was photographed. The dates are real — read from the files, not typed in.

40 days photographed

  1. Utilities and servicesNovember 21, 20253 photos

    Recessed board in a niche finished in porcelain tile · Wall of horizontal timber slats and porcelain flooring

  2. Utilities and servicesNovember 17, 20256 photos

    Bedroom ceiling with wiring run and light fittings · Fully timber-clad facade with guttering and a porch

  3. Utilities and servicesNovember 8, 20253 photos

    Heating cable snaked over foil insulation on the terrace · Assembled ETI board with Eaton breakers and power cables

  4. FinishingNovember 6, 20252 photos

    Two white doors in concealed frames and black switches · Two-step timber porch and stained cladding to the terrace plinth

  5. Site preparationNovember 5, 20251 photo

    Removing the timber terrace decking and preparing the base

  6. Floor screedNovember 4, 20256 photos

    Hallway with floor protection, ready for screeding · Living room with painted walls, cornice and a pendant light

  7. FinishingNovember 2, 20251 photo

    Hallway laminate partly covered with protective film

  8. FinishingOctober 31, 20252 photos

    Narrow window with an anthracite frame in timber trims with a sill · Wall-mounted split unit and a slot ventilation grille

  9. Utilities and servicesOctober 30, 20252 photos

    Base preparation and service runs in the entrance area · Heating and water supply installation in the plant room

  10. FinishingOctober 29, 20251 photo

    Cylindrical wood-burning stove on a glass hearth plate in the living room

  11. FinishingOctober 28, 20251 photo

    Part of the planken facade, temporary porch with steps and railings

  12. FinishingOctober 24, 20251 photo

    Anthracite glazed entrance door with foamed joints

  13. Utilities and servicesOctober 21, 20255 photos

    Water and heating installation in the bathroom · Timber facade, paving and rolls of geotextile

  14. FinishingOctober 16, 20251 photo

    Horizontal planken on the facade and a mineral wool insulated plinth

Documents

The contract, the estimate and the certificates live in the account, not in somebody's messenger. This project's archive holds 26 scanned documents — the documents themselves are closed in the demo.

  • Contract and annexesHidden
  • EstimateHidden
  • Certificates of completionHidden
  • Material specificationsHidden
  • As-built documentationHidden

Work in progress

Each stage is dates and frames from the site. These were shot for the job, not for a website, which is why some of them look exactly like a building site looks.

01

Site preparation

July 2025 — November 20253 photos

Work in progress

Setting out the foundation with a measuring tape on site

grounds · July 18, 2025

Marked-out foundation base with materials laid out nearby

outdoors · October 11, 2025

Removing the timber terrace decking and preparing the base

terrace · November 5, 2025

02

Utilities and services

May 2025 — November 202529 photos

Work in progress

Pressure-testing the water supply with a pump and gauge via a ball valve

May 28, 2025

Partition framing, floor joists and cable in conduit

June 2, 2025

Running electrical cables through the floor

June 27, 2025

Recessed distribution board with multi-row breakers and RCDs

June 27, 2025

Electricity metering unit on a concrete pole with aerial bundled cable

plot · July 3, 2025

Consumer unit and cable runs in the plant room wall

July 3, 2025

Ceiling wiring in flexible metal conduit with junction boxes

July 3, 2025

Hallway with OSB sheathing, conduit cable and back boxes

hallway · August 1, 2025

Water supply manifold with ball valves and a water meter

August 1, 2025

Plasterboard to walls and ceiling with layout marks for fittings

room · August 6, 2025

Metal ceiling frame, insulation and installed balcony door

August 6, 2025

Moisture-resistant plasterboard in the bathroom with tap outlets

bathroom · September 13, 2025

Electrical wiring and lighting points in the bathroom

bathroom · September 13, 2025

Bathroom with services run in beside the window opening

bathroom · September 19, 2025

Copper ball valve with a blue handle on a pipe

September 19, 2025

Water supply installation with an expansion vessel in the bathroom

bathroom · September 19, 2025

Bathroom with water supply and drainage connections in place

bathroom · September 22, 2025

Plumbing and electrical first fix in the bathroom

bathroom · September 24, 2025

Installing a steel sink and marking out water pipe runs

bathroom · October 8, 2025

Electrical wiring with cables laid out across the floor

October 9, 2025

Underfloor heating mat with its label on an OSB base

October 9, 2025

Trench with the incoming power cable outside

October 15, 2025

Water and heating installation in the bathroom

bathroom · October 21, 2025

Base preparation and service runs in the entrance area

entrance · October 30, 2025

Heating and water supply installation in the plant room

utility room · October 30, 2025

Heating cable snaked over foil insulation on the terrace

balcony · November 8, 2025

Assembled ETI board with Eaton breakers and power cables

November 8, 2025

Bedroom ceiling with wiring run and light fittings

bedroom · November 17, 2025

Recessed board in a niche finished in porcelain tile

November 21, 2025

03

First fix

May 2025 — November 202529 photos

Work in progress

Wall framing with bracing and floor joists over a crushed stone bed

May 17, 2025

House shell in OSB sheathing with a metal tile roof

plot · May 22, 2025

Filling the wall frame with mineral wool and sheathing the floor in OSB

May 28, 2025

Insulated walls, fitted windows and Parobarrier film on the floor

May 28, 2025

General view of the site with a site cabin and stacked timber

plot · May 28, 2025

OSB and metal tile facade, unloading dry mixes

facade · June 2, 2025

External wall on pad foundations with drainage stubs

facade · June 23, 2025

Cable bundles across ceiling and walls above the OSB subfloor

June 27, 2025

Weathertight shell: SIP panels, roof, windows and doors

facade · July 10, 2025

Frame of the future terrace on steel posts at the entrance

facade · July 18, 2025

Breather membrane over the frame and a glazed uPVC door

July 18, 2025

Notched joint in the sole plate timbers with a measuring rule

plot · July 18, 2025

Preparing ceiling and walls for finishing in the open-plan space

August 1, 2025

Panoramic window-door unit and membrane over ceiling joists

August 1, 2025

Stack of plasterboard and packs of mineral wool before boarding the ceiling

August 1, 2025

Walls and ceiling fully lined in moisture-resistant plasterboard

August 6, 2025

Rafter structure with struts and an OSB subfloor in the loft

August 15, 2025

Corner of the house with metal tile roofing and projecting rafter tails

facade · August 15, 2025

Living room with plasterboard walls and panoramic windows to the terrace

living room · August 21, 2025

Terrace with timber railings and an OSB deck base

balcony · August 26, 2025

Filled bedroom walls and balcony doors still in film

bedroom · September 1, 2025

Laying underlay and floor covering in the room

room · September 1, 2025

Front loader levelling ground beside the finished shell

plot · September 19, 2025

Bathroom with tiled walls, viewed from the doorway

bathroom · September 24, 2025

Vertical battens for the cladding and paving works underway

facade · October 2, 2025

Timber wall frame with sheathing, front view

October 8, 2025

Laying paving with service inspection covers along the facade

facade · October 11, 2025

Fixing timber planken along the wall over the concrete apron

facade · October 15, 2025

Distribution board with breakers and protective devices in the plant room

November 8, 2025

04

Floor screed

November 20251 photo

Work completed

Hallway with floor protection, ready for screeding

corridor · November 4, 2025

05

Plastering

August 2025 — September 20257 photos

Work completed

Bedroom prepared for final wall and ceiling finishes

bedroom · August 26, 2025

Plastered hallway walls and a plasterboard ceiling with joints filled

hallway · August 30, 2025

Plastered bedroom walls, window with sill, trestles in the middle

bedroom · September 1, 2025

Bathroom corner in plasterboard with a mounting box

bathroom · September 13, 2025

Plaster-levelled walls and a concrete floor screed

bedroom · September 13, 2025

REHAU window reveals plastered and filled

September 14, 2025

Bathroom with glazing fitted in the window opening

bathroom · September 24, 2025

06

Finishing

August 2025 — March 202626 photos

Work in progress

Completed external envelope with a hip roof and windows

facade · August 15, 2025

Filled walls and panoramic balcony doors still in film

September 1, 2025

REHAU window-door unit and plastered reveals from inside

September 14, 2025

Bathroom with marble-effect ceramic tiling

bathroom · September 22, 2025

Marble-effect porcelain, a recessed shelf and the cistern boxing

bathroom · September 24, 2025

Paving along the house and the concrete kerb of the apron

plot · October 2, 2025

Underfloor heating mats and the first laminate boards

October 9, 2025

Label of the 318 W AHT heating mat on OSB

October 9, 2025

Infrared film with a sensor and the first rows of flooring

October 9, 2025

Cladding the wall with planken from scaffolding beside the window

facade · October 15, 2025

Horizontal planken on the facade and a mineral wool insulated plinth

facade · October 16, 2025

Timber facade, paving and rolls of geotextile

plot · October 21, 2025

Laminate laid in the bedroom with cable tails for outlets

bedroom · October 21, 2025

Heating mat on the bathroom floor, shower and basin installed

bathroom · October 21, 2025

Painted bedroom walls, laminate and a radiator connection

bedroom · October 21, 2025

Anthracite glazed entrance door with foamed joints

facade · October 24, 2025

Part of the planken facade, temporary porch with steps and railings

facade · October 28, 2025

Cylindrical wood-burning stove on a glass hearth plate in the living room

living room · October 29, 2025

Narrow window with an anthracite frame in timber trims with a sill

facade · October 31, 2025

Hallway laminate partly covered with protective film

hallway · November 2, 2025

Living room with painted walls, cornice and a pendant light

living room · November 4, 2025

Two white doors in concealed frames and black switches

hallway · November 6, 2025

Two-step timber porch and stained cladding to the terrace plinth

facade · November 6, 2025

Fully timber-clad facade with guttering and a porch

facade · November 17, 2025

Laying wood-effect porcelain on the terrace with tile spacers

balcony · November 17, 2025

Wall of horizontal timber slats and porcelain flooring

hallway · November 21, 2025

07

Furniture and fittings

November 20258 photos

Work in progress

Bedroom with oak-effect laminate, skirting and panoramic doors

bedroom · November 4, 2025

Bed with mattress in the painted bedroom with a balcony unit

bedroom · November 4, 2025

Living room with a corner sofa, coving and a globe pendant

living room · November 4, 2025

Oak engineered board and a bed covered in protective film

bedroom · November 4, 2025

Installed air conditioner and a socket block for the TV

living room · November 17, 2025

Living room with a TV, air conditioner and cast-iron stove

living room · November 17, 2025

Built-in cabinet above the bed with concealed LED lighting

bedroom · November 17, 2025

Built-in unit with shelves and timber detailing behind the headboard

bedroom · November 21, 2025

08

Completed

October 2025 — March 20261 photo

Completed and handed over — Final photographs, after cleaning and handover.

Wall-mounted split unit and a slot ventilation grille

October 31, 2025

Want the same account for your project?

We open the account on day one: the client sees stages, dates and photographs without waiting for a call from the site manager.

  • Access from the first day of work
  • Photo reports from site, not «all good»
  • Estimate, payments and balance in one place
+380 67 679 59 79

For example, +38 067 123 45 67

By sending this request you agree to our privacy policy.

Get a cost estimate