House construction in Demydiv
House in Demydiv
A single-storey timber-frame house in Demydiv, Kyiv region: from setting out the foundation and erecting the frame through to full interior finishing, furnishing and site landscaping. The complete cycle was carried out — mineral wool insulation, electrics with distribution boards and backup power from an inverter with battery storage, water supply, electric underfloor heating, timber planken cladding, a metal tile roof, paving and fencing. Work ran from May 2025 to March 2026.
Private house construction in Kyiv and the region- Start
- May 2025
- Completed
- March 2026
- Photo record
- 10 months
- Stages
- 8
- Photos
- 158
Client
- Project address
- ••••••••• St, ••
- Type
- House
- Rooms
- 16
- Duration
- 10 months
- Stages
- 8
- Photo report
- 158
- Documents
- 26
The client's name, photo and exact address are withheld. In their own account they see all of it.
Responsible for the project
Viacheslav MelnykFounder of Archideal · general contractorRuns the project himself: signs off stages, signs the certificates, answers the phone.
+380 67 679 59 79The account as the owner saw it on November 21, 2025: some stages closed, one under way, the rest ahead. Nothing has been altered — anything photographed later is simply hidden.
- Stages
- 8
- Photos
- 104 / 158
- Approvals
- 17
- Documents
- 26
Stage schedule
As of November 21, 2025 · 104 of 158 photos
May 2025 — March 2026
The bars are built from the dates the photographs were taken, not drawn by hand — which is why stages overlap. On a real site something is always being finished while the next trade has already started.
Estimate
In a working account this shows amounts per stage, payments made and the balance. In the demo they are hidden.
| Stage | Status | Amount |
|---|---|---|
| Site preparation | In progress | 1 ******₴ |
| Utilities and services | In progress | 9 ******₴ |
| First fix | In progress | 4 ******₴ |
| Floor screed | Completed | 4 ******₴ |
| Plastering | Completed | 3 ******₴ |
| Finishing | In progress | 6 ******₴ |
| Furniture and fittings | In progress | 9 ******₴ |
| Completed | In progress | 3 ******₴ |
| Total | 6 *******₴ |
The amounts are hidden because this is someone else's project. You will see your own in your estimate, not on a website.
Approvals
Every decision that affects the money or the look is logged as its own item. Until the client marks it approved, work on that item does not start.
16 approved · 1 returned
| Item | Approved by | Date | Status |
|---|---|---|---|
| Water and drainage pointsUtilities and services | Engineer | June 3, 2025 | Approved |
| Electrical layout and outletsUtilities and services | Client | June 18, 2025 | Approved |
| Floor and ceiling levelsFirst fix | Client | June 27, 2025 | Approved |
| Demolition plan and setting outSite preparation | Client | July 23, 2025 | Approved |
| Heating layoutUtilities and services | Client | August 1, 2025 | Approved |
| Partition build-upFirst fix | Engineer | August 18, 2025 | Approved |
| Survey and floor planSite preparation | Designer | August 24, 2025 | Approved |
| Plaster typePlastering | Engineer | August 31, 2025 | Returned for revision |
| Reveals and external cornersPlastering | Client | September 1, 2025 | Approved |
| Plaster typePlastering · after revision | Engineer | September 6, 2025 | Approved |
| Floor finishFinishing | Client | September 17, 2025 | Approved |
| Wall colourFinishing | Client | September 20, 2025 | Approved |
| Screed grade and thicknessFloor screed | Engineer | November 4, 2025 | Approved |
| Light fittingsFurniture and fittings | Client | November 7, 2025 | Approved |
| Sanitaryware modelsFurniture and fittings | Designer | November 8, 2025 | Approved |
| Doors and hardwareFinishing | Designer | November 11, 2025 | Approved |
| Kitchen drawingsFurniture and fittings | Engineer | November 13, 2025 | Approved |
The approvals shown here are an example of how the mechanism works: the photographs do not record what was actually signed off on this project. Your account will carry your own history.
On site
- Site managerdaily supervision and photo reports
- Project managerestimate, schedule, contact with the client
- Engineerdrawings and details
Rooms
How many frames each part of the project accounts for.
- bedroom21
- facade21
- bathroom18
- living room18
- kitchen13
- plot10
- hallway9
- balcony3
- room2
- entrance2
- grounds1
- outdoors1
- terrace1
- utility room1
- corridor1
- living-bedroom1
Site log
Every day the site was photographed. The dates are real — read from the files, not typed in.
40 days photographed
Utilities and servicesNovember 21, 20253 photos
Recessed board in a niche finished in porcelain tile · Wall of horizontal timber slats and porcelain flooring
Utilities and servicesNovember 17, 20256 photos
Bedroom ceiling with wiring run and light fittings · Fully timber-clad facade with guttering and a porch
Utilities and servicesNovember 8, 20253 photos
Heating cable snaked over foil insulation on the terrace · Assembled ETI board with Eaton breakers and power cables
FinishingNovember 6, 20252 photos
Two white doors in concealed frames and black switches · Two-step timber porch and stained cladding to the terrace plinth
Site preparationNovember 5, 20251 photo
Removing the timber terrace decking and preparing the base
Floor screedNovember 4, 20256 photos
Hallway with floor protection, ready for screeding · Living room with painted walls, cornice and a pendant light
FinishingNovember 2, 20251 photo
Hallway laminate partly covered with protective film
FinishingOctober 31, 20252 photos
Narrow window with an anthracite frame in timber trims with a sill · Wall-mounted split unit and a slot ventilation grille
Utilities and servicesOctober 30, 20252 photos
Base preparation and service runs in the entrance area · Heating and water supply installation in the plant room
FinishingOctober 29, 20251 photo
Cylindrical wood-burning stove on a glass hearth plate in the living room
FinishingOctober 28, 20251 photo
Part of the planken facade, temporary porch with steps and railings
FinishingOctober 24, 20251 photo
Anthracite glazed entrance door with foamed joints
Utilities and servicesOctober 21, 20255 photos
Water and heating installation in the bathroom · Timber facade, paving and rolls of geotextile
FinishingOctober 16, 20251 photo
Horizontal planken on the facade and a mineral wool insulated plinth
Documents
The contract, the estimate and the certificates live in the account, not in somebody's messenger. This project's archive holds 26 scanned documents — the documents themselves are closed in the demo.
- Contract and annexesHidden
- EstimateHidden
- Certificates of completionHidden
- Material specificationsHidden
- As-built documentationHidden
Work in progress
Each stage is dates and frames from the site. These were shot for the job, not for a website, which is why some of them look exactly like a building site looks.
Site preparation
July 2025 — November 20253 photosWork in progress
Setting out the foundation with a measuring tape on site
grounds · July 18, 2025
Marked-out foundation base with materials laid out nearby
outdoors · October 11, 2025
Removing the timber terrace decking and preparing the base
terrace · November 5, 2025
Utilities and services
May 2025 — November 202529 photosWork in progress
Pressure-testing the water supply with a pump and gauge via a ball valve
May 28, 2025
Partition framing, floor joists and cable in conduit
June 2, 2025
Running electrical cables through the floor
June 27, 2025
Recessed distribution board with multi-row breakers and RCDs
June 27, 2025
Electricity metering unit on a concrete pole with aerial bundled cable
plot · July 3, 2025
Consumer unit and cable runs in the plant room wall
July 3, 2025
Ceiling wiring in flexible metal conduit with junction boxes
July 3, 2025
Hallway with OSB sheathing, conduit cable and back boxes
hallway · August 1, 2025
Water supply manifold with ball valves and a water meter
August 1, 2025
Plasterboard to walls and ceiling with layout marks for fittings
room · August 6, 2025
Metal ceiling frame, insulation and installed balcony door
August 6, 2025
Moisture-resistant plasterboard in the bathroom with tap outlets
bathroom · September 13, 2025
Electrical wiring and lighting points in the bathroom
bathroom · September 13, 2025
Bathroom with services run in beside the window opening
bathroom · September 19, 2025
Copper ball valve with a blue handle on a pipe
September 19, 2025
Water supply installation with an expansion vessel in the bathroom
bathroom · September 19, 2025
Bathroom with water supply and drainage connections in place
bathroom · September 22, 2025
Plumbing and electrical first fix in the bathroom
bathroom · September 24, 2025
Installing a steel sink and marking out water pipe runs
bathroom · October 8, 2025
Electrical wiring with cables laid out across the floor
October 9, 2025
Underfloor heating mat with its label on an OSB base
October 9, 2025
Trench with the incoming power cable outside
October 15, 2025
Water and heating installation in the bathroom
bathroom · October 21, 2025
Base preparation and service runs in the entrance area
entrance · October 30, 2025
Heating and water supply installation in the plant room
utility room · October 30, 2025
Heating cable snaked over foil insulation on the terrace
balcony · November 8, 2025
Assembled ETI board with Eaton breakers and power cables
November 8, 2025
Bedroom ceiling with wiring run and light fittings
bedroom · November 17, 2025
Recessed board in a niche finished in porcelain tile
November 21, 2025
First fix
May 2025 — November 202529 photosWork in progress
Wall framing with bracing and floor joists over a crushed stone bed
May 17, 2025
House shell in OSB sheathing with a metal tile roof
plot · May 22, 2025
Filling the wall frame with mineral wool and sheathing the floor in OSB
May 28, 2025
Insulated walls, fitted windows and Parobarrier film on the floor
May 28, 2025
General view of the site with a site cabin and stacked timber
plot · May 28, 2025
OSB and metal tile facade, unloading dry mixes
facade · June 2, 2025
External wall on pad foundations with drainage stubs
facade · June 23, 2025
Cable bundles across ceiling and walls above the OSB subfloor
June 27, 2025
Weathertight shell: SIP panels, roof, windows and doors
facade · July 10, 2025
Frame of the future terrace on steel posts at the entrance
facade · July 18, 2025
Breather membrane over the frame and a glazed uPVC door
July 18, 2025
Notched joint in the sole plate timbers with a measuring rule
plot · July 18, 2025
Preparing ceiling and walls for finishing in the open-plan space
August 1, 2025
Panoramic window-door unit and membrane over ceiling joists
August 1, 2025
Stack of plasterboard and packs of mineral wool before boarding the ceiling
August 1, 2025
Walls and ceiling fully lined in moisture-resistant plasterboard
August 6, 2025
Rafter structure with struts and an OSB subfloor in the loft
August 15, 2025
Corner of the house with metal tile roofing and projecting rafter tails
facade · August 15, 2025
Living room with plasterboard walls and panoramic windows to the terrace
living room · August 21, 2025
Terrace with timber railings and an OSB deck base
balcony · August 26, 2025
Filled bedroom walls and balcony doors still in film
bedroom · September 1, 2025
Laying underlay and floor covering in the room
room · September 1, 2025
Front loader levelling ground beside the finished shell
plot · September 19, 2025
Bathroom with tiled walls, viewed from the doorway
bathroom · September 24, 2025
Vertical battens for the cladding and paving works underway
facade · October 2, 2025
Timber wall frame with sheathing, front view
October 8, 2025
Laying paving with service inspection covers along the facade
facade · October 11, 2025
Fixing timber planken along the wall over the concrete apron
facade · October 15, 2025
Distribution board with breakers and protective devices in the plant room
November 8, 2025
Floor screed
November 20251 photoWork completed
Hallway with floor protection, ready for screeding
corridor · November 4, 2025
Plastering
August 2025 — September 20257 photosWork completed
Bedroom prepared for final wall and ceiling finishes
bedroom · August 26, 2025
Plastered hallway walls and a plasterboard ceiling with joints filled
hallway · August 30, 2025
Plastered bedroom walls, window with sill, trestles in the middle
bedroom · September 1, 2025
Bathroom corner in plasterboard with a mounting box
bathroom · September 13, 2025
Plaster-levelled walls and a concrete floor screed
bedroom · September 13, 2025
REHAU window reveals plastered and filled
September 14, 2025
Bathroom with glazing fitted in the window opening
bathroom · September 24, 2025
Finishing
August 2025 — March 202626 photosWork in progress
Completed external envelope with a hip roof and windows
facade · August 15, 2025
Filled walls and panoramic balcony doors still in film
September 1, 2025
REHAU window-door unit and plastered reveals from inside
September 14, 2025
Bathroom with marble-effect ceramic tiling
bathroom · September 22, 2025
Marble-effect porcelain, a recessed shelf and the cistern boxing
bathroom · September 24, 2025
Paving along the house and the concrete kerb of the apron
plot · October 2, 2025
Underfloor heating mats and the first laminate boards
October 9, 2025
Label of the 318 W AHT heating mat on OSB
October 9, 2025
Infrared film with a sensor and the first rows of flooring
October 9, 2025
Cladding the wall with planken from scaffolding beside the window
facade · October 15, 2025
Horizontal planken on the facade and a mineral wool insulated plinth
facade · October 16, 2025
Timber facade, paving and rolls of geotextile
plot · October 21, 2025
Laminate laid in the bedroom with cable tails for outlets
bedroom · October 21, 2025
Heating mat on the bathroom floor, shower and basin installed
bathroom · October 21, 2025
Painted bedroom walls, laminate and a radiator connection
bedroom · October 21, 2025
Anthracite glazed entrance door with foamed joints
facade · October 24, 2025
Part of the planken facade, temporary porch with steps and railings
facade · October 28, 2025
Cylindrical wood-burning stove on a glass hearth plate in the living room
living room · October 29, 2025
Narrow window with an anthracite frame in timber trims with a sill
facade · October 31, 2025
Hallway laminate partly covered with protective film
hallway · November 2, 2025
Living room with painted walls, cornice and a pendant light
living room · November 4, 2025
Two white doors in concealed frames and black switches
hallway · November 6, 2025
Two-step timber porch and stained cladding to the terrace plinth
facade · November 6, 2025
Fully timber-clad facade with guttering and a porch
facade · November 17, 2025
Laying wood-effect porcelain on the terrace with tile spacers
balcony · November 17, 2025
Wall of horizontal timber slats and porcelain flooring
hallway · November 21, 2025
Furniture and fittings
November 20258 photosWork in progress
Bedroom with oak-effect laminate, skirting and panoramic doors
bedroom · November 4, 2025
Bed with mattress in the painted bedroom with a balcony unit
bedroom · November 4, 2025
Living room with a corner sofa, coving and a globe pendant
living room · November 4, 2025
Oak engineered board and a bed covered in protective film
bedroom · November 4, 2025
Installed air conditioner and a socket block for the TV
living room · November 17, 2025
Living room with a TV, air conditioner and cast-iron stove
living room · November 17, 2025
Built-in cabinet above the bed with concealed LED lighting
bedroom · November 17, 2025
Built-in unit with shelves and timber detailing behind the headboard
bedroom · November 21, 2025
Completed
October 2025 — March 20261 photoCompleted and handed over — Final photographs, after cleaning and handover.
Wall-mounted split unit and a slot ventilation grille
October 31, 2025
Want the same account for your project?
We open the account on day one: the client sees stages, dates and photographs without waiting for a call from the site manager.
- Access from the first day of work
- Photo reports from site, not «all good»
- Estimate, payments and balance in one place